Milestones
Milestones mark critical points in your project, from contract deliverables to site handovers. In Aphex, they work just like Tasks, so you can assign all the same details: like Owners, Resources, Subcontractors, Blockers, Work Areas, and Delays.
Milestones can include a fixed Target Date, giving you a reference point to track progress against. The Gantt will summarise & highlight whether you're on track or slipping, across all your Milestones.
Creating Milestones
To create a Milestone, convert any existing Task or Subtask, or import Milestones directly from your Master Schedule.
Create a Milestone from the Gantt:
Hover over the task name
Click
and select
Convert to Milestone
Milestone Target Dates
Each Milestone can be assigned a Target Date: the original or ideal date you’re aiming for, often pulled from a Master or Contract Schedule. The Target Date marker changes colour based on performance, helping you see at a glance how things are progressing against the plan.
To set a Target Date:
Right click a Milestone and select
View Details
In the Task Panel that opens, locate the
Target Date
sectionToggle
Set Target Date
Pick the date
To See Target Date Variance on the Gantt:
If your Milestone has slipped the Target Date marker will appear as
If your Milestone is on track, Target Date marker will appear as
Use the
+
/-
indicators to see how many days a Milestone is ahead or behind
Tracking Milestone Performance
Use the Milestone Panel to compare current Milestone Dates to Target Dates, or pervious Weekly Versions to see how things have shifted over time - and spot the impact of today's changes on future Milestones, even if they're outside of your View.
Open the Milestone Panel:
On the Gantt, select the
Milestone Icon in the right-hand panel
This opens the
Milestone Panel
, showing Milestones across the ProjectClick the
⌄
next to any Milestone to expand its history and see how it’s changed over timeOpen the
config menu to toggle filters for delayed or improved Milestones
Target Date Comparison:
In the Milestones Panel, click into the
Compare To
dropdownSelect
Target Date
Instantly see how many days ahead/behind for each Milestone, compared to their Target Dates
Baseline Comparison:
In the Milestones Panel, click into the
Compare To
dropdownSelect
Previously Published Version
Instantly view the variance between current and baseline dates
Critical Path Overlay
Turn on the Critical Path Overlay to highlight the short term path to any Milestone. The critical path will light up in gold, and everything else fades to blue - so it's easy to see what's critical and what's not. You can view paths for all Milestones or focus on one at a time.
To turn on the Critical Path
Open the Gantt and click
Select
Critical Path
to highlight all Milestone paths in goldOr click the
>
to choose specific Milestone pathways to highlight individually
Filter to Milestones
To set a Milestone filter:
Click
and
Select
Milestone
in the first dropdownSelect from
Is True
orIs False
in the second dropdown
Pre-made Milestones View:
Your Project comes with a pre-made Upcoming Milestones View.
Click
+ Views
within the open View TabsSelect
Upcoming Milestones View