# Milestones

{% hint style="info" %}
**Who can use this feature**

All Project users can convert a Task to a Milestone.

***

Task Owners, Assignees and Admins can edit the Milestone Target Date.
{% endhint %}

Milestones mark critical points in your project, from contract deliverables to site handovers. In Aphex, they work just like Tasks, so you can assign all the same details: like Owners, Resources, Subcontractors,  Blockers, Work Areas, and Delays.

Milestones can include a fixed Target Date, giving you a reference point to track progress against. The Gantt will summarise & highlight whether you're on track or slipping, across all your Milestones.

## Creating Milestones

***

To create a Milestone, convert any existing Task or Subtask, or import Milestones directly from your Master Schedule.

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FW3EqkeBwV4rLoIduBKyn%2FConvert%20to%20milestone.svg?alt=media&#x26;token=3f8d982a-115e-43ba-aa2d-061abd5f211c" alt=""><figcaption></figcaption></figure>

**Create a Milestone from the Gantt:**

* Hover over the task name
* Click  <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FunU6FaTKiBE8xXhg6N0j%2Foverflow%20button.svg?alt=media&#x26;token=5a3f3ce9-9039-4119-a28e-f4d2a2189ced" alt="" data-size="line"> and select `Convert to Milestone`

<details>

<summary>Milestone Conversion Logic</summary>

* Each Milestone spans at least one day, just like every Task in your plan.
* Only Tasks and Subtasks can be converted to Milestones
* When converted, the Milestone keeps all its original Task properties, including duration, delay history, owner, and assigned resources
* Attempting to set the Duration to 0 will also trigger the Convert to Milestone flow
* You can convert a Milestone back into a Task or Subtask at any time

</details>

## Milestone Target Dates

***

Each Milestone can be assigned a Target Date: the original or ideal date you’re aiming for, often pulled from a Master or Contract Schedule. The Target Date marker changes colour based on performance, helping you see at a glance how things are progressing against the plan.

#### **To set a Target Date:**

* Right click a Milestone and select `View Details`
* In the Task Panel that opens, locate the `Target Date` section
* Toggle  <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FrvTcctNRDtoOHaw7U9zU%2FTheme%3DLight%2C%20Size%3DRegular%2C%20State%3DOn.svg?alt=media&#x26;token=d08029bc-cd20-4401-bc69-8ded58cdca38" alt="" data-size="line"> `Set Target Date`
* Pick the date

#### **To See Target Date Variance on the Gantt:**

* If your Milestone has slipped the Target Date marker will appear as <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FnRvmcVIG0LgC1JQpKw4F%2FFrame%203275.svg?alt=media&#x26;token=e6ebe564-e5fe-4168-b990-a5dde96b7962" alt="" data-size="line">
* If your Milestone is on track, Target Date marker will appear as ![](https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FAHn9ZIJdUROV9bPXC0ru%2FFrame%203275%20\(1\).svg?alt=media\&token=93489ac9-6a49-4b53-aa0a-e836f54528df)
* Use the `+`/`-` indicators to see how many days a Milestone is ahead or behind

<details>

<summary>Target Date Logic </summary>

* Target Dates will show green if:
  * The Milestone End Date matches the Target Date
  * The Milestone End Date is before the Target Date
* Target Dates will show red if:
  * The Milestone End Date is after the Target Date
* On the Gantt, a Variance Number will show how many days the Milestone has slipped or improved by
* Target Date Icons & Variance update in real time as changes are made to the plan

</details>

## Tracking Milestone Performance

***

Use the Milestone Panel to compare current Milestone Dates to Target Dates, or pervious Weekly Versions to see how things have shifted over time - and spot the impact of today's changes on future Milestones, even if they're outside of your View.&#x20;

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2Fn6Yxz35em8nbIsrSVeWJ%2FMilestone%20Panel.svg?alt=media&#x26;token=178e770a-4ae3-4ba7-8853-1fa74ccb936b" alt=""><figcaption></figcaption></figure>

#### Open the Milestone Panel:

* On the Gantt, select the ![](https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FqKNMvhxEzQ4JAskC9dFB%2FMilestone%20Icon%20\(2\).svg?alt=media\&token=54f100b0-047d-48f3-b301-36be5e1e81bd) Milestone Icon in the right-hand panel
* This opens the `Milestone Panel`, showing Milestones across the Project
* Click the `⌄` next to any Milestone to expand its history and see how it’s changed over time
  * Open the <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FMHITYZSRXlaIXMvqrJZu%2FIcon%20Buttons%20(4).svg?alt=media&#x26;token=ac847fe0-006b-4ff0-b70a-8758c4ca625d" alt="" data-size="line"> config menu to toggle filters for delayed or improved Milestones

#### Target Date Comparison:

* In the Milestones Panel, click into the `Compare To` dropdown
* Select `Target Date`
* Instantly see how many days ahead/behind for each Milestone, compared to their Target Dates

#### Baseline Comparison:

* In the Milestones Panel, click into the `Compare To` dropdown
* Select `Previously Published Version`
* Instantly view the variance between current and baseline dates

See also: <a href="../imports-and-exports#exporting-milestones" class="button secondary">Export Milestone Data</a>

<details>

<summary>Configuring the Milestone Panel</summary>

**Date Range:** Controls which Milestones appear in the list. You can show only those within your current Gantt view, all future Milestones, or every Milestone in the project.\
\
**Group By:** Organises your Milestones into sections. Choosing Performance vs Target splits them into four groups based on how the Milestone's end date compares to its Target Date:

* **Approaching Target**: the end date is before the Target Date
* **On Target**: the end date matches the Target Date exactly
* **Behind Target**: the end date has passed the Target Date
* **No Target**: no Target Date has been set

You can also group by Owner, Subcontractor, Folder, or Package.\
\
**Sort By**: Controls the order Milestones appear within each group. Sort by date or variance, in ascending or descending order.\
\
**Spotlight Milestones with Variance**: When toggled on, this highlights Milestones that have slipped or improved. You can choose to spotlight just slippage, just improvements, or both.\
\
Your configuration is saved automatically per user, so the panel will remember your preferences next time.

</details>

## Critical Path Overlay

***

Turn on the Critical Path Overlay to highlight the short term path to any Milestone. The critical path will light up in gold, and everything else fades to blue - so it's easy to see what's critical and what's not. You can view paths for all Milestones or focus on one at a time.

**To turn on the Critical Path**

* Open the Gantt and click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FrG483tQu3ZGYIlP5D1Lq%2FView%20Sub%20Nav%20Buttons%20(6).svg?alt=media&#x26;token=e9e3bccb-b93e-43ec-b54d-3f3bc509f5f3" alt="" data-size="line">
* Select `Critical Path` to highlight all Milestone paths in gold
* Or click the `>` to choose specific Milestone pathways to highlight individually

## Filter to Milestones

***

#### To set a Milestone filter:

* Click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2F1uSzhSb5aSNnZd5vTaGB%2FFilter%20Button.svg?alt=media&#x26;token=8ddd7f1c-0296-4af2-bdeb-d08d56fc56b6" alt="" data-size="line"> and <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FbVv9qtyepRHQfkVwypud%2FText%20Buttons%20(2).svg?alt=media&#x26;token=fce29edb-8b74-4d75-bfa0-d8ad7292c94b" alt="" data-size="line">
* Select `Milestone` in the first dropdown
* Select from `Is True` or `Is False` in the second dropdown

#### Pre-made Milestones View:

Your Project comes with a pre-made Upcoming Milestones View.

* Click `+ Views` within the open View Tabs
* Select `Upcoming Milestones View`

See also: creating & sharing <a href="view-controls" class="button secondary">Views</a>

<details>

<summary>Filter Breakdown</summary>

| Filter     | Operator                   | Value        |
| ---------- | -------------------------- | ------------ |
| Milestones | <p>Is True<br>Is False</p> | Multi-Select |

</details>