PPC Dashboard
Delay Breakdown
Milestone Analysis
Resources




The Delay Breakdown shows where delay days are coming from, sorted by impact, so you can see your biggest problem areas before drilling into who's responsible.
Bars are sorted largest impact first, giving you an immediate picture of which delay reasons are having the most effect on the project.
Use the filter bar to narrow the report to a specific part of the project or a specific date range.
To set a date range:
Use the Date Range picker in the filter bar to choose the window you want to analyse
To filter by subcontractor, owner, or other dimensions:
Click Filters in the top right corner
Select one or more values - you can filter by: Task Owner, Subcontractor, Shift, Package, Assignee, Folder, and Location
Applied filters appear as removable tags; select Clear Filters to reset
To change which publication the report is anchored to:
Use the Publication selector in the filter bar
Defaults to the latest published version
See also
Below the chart, two pivot tables let you see exactly which subcontractors or task owners are behind each delay reason.
Click any reason row in the Delays by Reason & Subcontractor or Delays by Reason & Task Owner table
The row expands to show a breakdown by Subcontractor or Task Owner
Each row shows the Tasks Delayed count and total Impact Days
Every chart and table can be exported as a CSV, with your active filters applied. Read our doc for a step by step guide.



The Resource reports show planned Labour, Plant, and Material demand across your project, helping you anticipate peaks and plan ahead.
Each resource report has two widgets: a stacked bar chart of total planned quantity by date, and a summary table with the minimum, maximum, and total planned quantity per resource.
The bar chart shows demand across time, with each resource type represented by its own colour.
The summary pivot table shows Minimum, Maximum, and Total planned quantity per resource - expandable to see each individual task-day.
The date range defaults to today + 6 weeks.
Use the date range picker to focus on a specific window of time.
To change the date range:
Use the Date Range picker in the filter bar
Select a start and end date for the period you want to analyse
The chart and table will update to reflect your selection
Below the chart, the Summary table breaks down planned quantities per resource, with the option to expand each row to see the day-by-day detail.
Each resource appears as a collapsed row showing three values across your selected date range:
Minimum Planned Quantity - the lowest planned quantity on any single day
Maximum Planned Quantity - the highest planned quantity on any single day
Planned Quantity - the total planned quantity across the full date range
To see the day-by-day breakdown for a resource:
Click the > arrow next to any resource name to expand it
Each date row shows the planned quantity for that specific day
Narrow the report to show resource demand for a specific part of the project.
To filter resource reports:
Click Filters in the top right corner
Select one or more values. You can filter by: Task Owner, Subcontractor, Shift, Package, Assignee, Folder, Labour, Plant, and Material
Applied filters appear as removable tags; select Clear Filters to reset
To change which publication the report is anchored to:
Use the Publication selector in the filter bar
Defaults to the latest published version
See also
Every chart and table can be exported as a CSV, with your active filters applied. Read our doc for a step by step guide.
Milestone Analysis shows the current status of every milestone in your project and how each date has shifted across publications.
Every milestone in the project appears as a row, showing its current date, target date, and whether it's ahead, on target, or behind.
To sort the table:
Click any column header to sort by that column
The Date Variance Over Time sparkline column isn't sortable
Use the status filter to focus on upcoming milestones, or get a full view of past and future ones.
The PPC Dashboard shows how well your team is delivering against the plan, tracking Task PPC and Task Day PPC across your publication history.
The PPC dashboard shows two KPIs side by side, Task PPC and Task Day PPC.
The trend chart tracks both Task PPC and Task Day PPC across your full publication history, so you can spot patterns and see whether performance is improving.
Use the toggle above the chart to switch between
Hover over any date on the chart




To filter milestones by time period:
Use the status filter in the top-right of the widget
Switch between Current (next 6 weeks), Future, Past, and All
Current is the default
To change which publication the report is anchored to:
Use the Publication selector in the filter bar
Defaults to the latest published version
Every chart and table can be exported as a CSV, with your active filters applied. Read our doc for a step by step guide.

A tooltip will appear showing:
The publication date
Task PPC - e.g. "0 / 9 completed"
Task Day PPC - e.g. "Avg. of 37 tasks"
Two tables show performance for the latest publication side by side, one grouped by Subcontractor, one by Task Owner.
Use the filter bar to focus on a specific part of the project. By package, folder, subcontractor, zone or more.
To filter the PPC Dashboard:
Click Filters at the top of the report
Select one or more values from the panel. You can filter by: Task Owner, Subcontractor, Shift, Package, Assignee, Folder, Location and Zone
Applied filters appear as removable tags; select Clear Filters to reset
To change which publication the report is anchored to:
Use the Publication selector in the filter bar
Defaults to the latest published version
Every chart and table can be exported as a CSV, with your active filters applied. Read our doc for a step by step guide.



External ID
The milestone's External ID
Date
The milestone's current end date
Target
The milestone's Target Date
Variance to Target
Number of days between the current date and Target Date
Status
Ahead, On Target, or Behind, based on variance to target
Date Variance Over Time
A sparkline showing how the milestone date has shifted each publication - improvements above the anchor line, delays below

Active Task - Count of active tasks assigned to that subcontractor / owner in the selected publication (including tasks that weren't due to finish in this period).
Not in this publication