If you've downloaded one of our free Power BI dashboards, you may have questions about how the PPC (Percent Plan Complete) is being calculated.
PPC shows you what percentage of your planned work actually got done between two dates (usually last week and this week). There are two ways to measure it:
This method looks at how many work days you completed as planned.
Example:
Let's say you have three tasks:
Task A: 3-day task, all days planned for the reference week
Task B: 2-day task, all days planned for the reference week
Task C: 4-day task, with 2 days planned for the reference week and 2 days the following week
What actually happened:
Task A: ✓ All 3 days completed during the reference week
Task B: ✗ Slipped—only 1 of the 2 planned days completed during the reference week
Task C: ✗ Slipped—only 1 of the 2 planned days completed during the reference week
How we calculate it:
Task A: 3 / 3 days = 100% PPC
Task B: 1 / 2 days = 50% PPC
Task C: 1 / 2 days = 50% PPC
Total PPC = Average(100%, 50%, 50%) = 66%
This method only counts tasks that were completely finished on schedule.
Example:
Let's say you have three tasks:
Task A: Final day planned to occur in the reference week
Task B: Final day planned to occur in the reference week
Task C: Final day planned to occur in the reference week
What actually happened:
Task A: ✓ Final day of task occurred in the reference week
Task B: ✗ Slipped—final day pushed to the following week
Task C: ✓ Final day of task occurred in the reference week
How we calculate it:
Task A: Completed = 100% PPC
Task B: Not Completed = 0% PPC
Task C: Completed = 100% PPC
Total PPC = Average(100%, 0%, 100%) = 66%