Who can use this feature?
Admin users can create, edit and archive the library of available Calendars.
Task Owners, Assignees and Admins can change the Calendar allocated to their Tasks.
Calendars define your project’s working and non-working days. Task durations are based only on the working days set in the assigned Calendar, so Tasks won’t be scheduled on non-working days.
Create a custom Calendar to set specific working and non-working days that match your project’s schedule.
Click your Project Title in the top left, then select Project Assets
Select Calendars from the menu
Click
Add a name and choose a colour to represent the Calendar
Pick your base Working Days
Click specific days on the Calendar to mark them as Working or Non-Working exceptions
Optionally,
Click Done once you're finished editing
The Calendar is added to the library of Calendars the team can assign to their Tasks
See also:
You can edit an existing Calendar to update working days, non-working days, change its name or colour.
Click your Project Title in the top left, then select Project Assets
Select Calendars from the menu
Hover over the existing Calendar
Assigning a Calendar to a Task sets its working days and controls when it can start or finish.
On the Gantt, navigate to the column picker and toggle on Calendar
Click a cell in the column to add a Calendar to the Task from the dropdown
See the non-working days appear with reduced opacity on the Task Bar
See also:
Filter by Calendar to focus on Tasks working to a certain schedule.
Click and
Select Calendar in the first dropdown
Select from Is or Is Not in the second dropdown
See also: create & share
Click then select Edit
If the Calendar is already in use, select whether to apply changes to existing Tasks or keep their current dates unchanged
Select your desired Calendar in the third dropdown
Six Day
Monday, Tuesday, Wednesday, Thursday, Friday, Saturday
Seven Day
Monday, Tuesday, Wednesday, Thursday, Friday, Saturday, Sunday
Save and hold dates on existing Tasks
The edited calendar will not be applied to any existing Tasks
Making any changes to the start date, end date or duration of a Task will apply the updated calendar to the Task
Save and force reschedule existing Tasks
The edited calendar will be applied to all future planned tasks and Tasks with days in progress
The edited calendar will not automatically be applied to any Tasks that have finished (no working days in progress or in the future)