PPC Dashboard

The PPC Dashboard shows how well your team is delivering against the plan, tracking Task PPC and Task Day PPC across your publication history.

View Plan Percent Complete (PPC)


The PPC dashboard shows two KPIs side by side, Task PPC and Task Day PPC.

How Task PPC and Task Day PPC are calculated

Task PPC counts tasks as pass or fail between two publication dates. A task scores 1 if all its planned working days in the window were completed, and 0 if not. The final PPC is the sum of those scores divided by the number of tasks planned in the window.

Task Day PPC takes the average percentage of planned working days completed per task. This means a task that was 80% done gets partial credit, rather than being counted as a failure.

Track Performance Over Time


The trend chart tracks both Task PPC and Task Day PPC across your full publication history, so you can spot patterns and see whether performance is improving.

To change the time range on the chart:

  • Use the toggle above the chart to switch between

To see the detail behind any data point:

  • Hover over any date on the chart

  • A tooltip will appear showing:

    • The publication date

    • Task PPC - e.g. "0 / 9 completed"

    • Task Day PPC - e.g. "Avg. of 37 tasks"

See also


Two tables show performance for the latest publication side by side, one grouped by Subcontractor, one by Task Owner.


Use the filter bar to focus on a specific part of the project. By package, folder, subcontractor, or more.

To filter the PPC Dashboard:

  • Click at the top of the report

  • Select one or more values from the panel. You can filter by: Task Owner, Subcontractor, Shift, Package, Assignee, Folder, and Location

  • Applied filters appear as removable tags; select to reset

To change which publication the report is anchored to:

  • Use the Publication selector in the filter bar

  • Defaults to the latest published version


Every chart and table can be exported as a CSV, with your active filters applied. Read our doc for a step by step guide.

Compare Performance by Subcontractor or Task Owner

Subcontractor & Task Owner Table Columns

In both the Subcontractor and Task Owner table, each row shows:

  • Task PPC (%)

  • Completed vs Planned Tasks (fraction)

  • Task Day PPC (%)

  • Active Task - Count of active tasks assigned to that subcontractor / owner in the selected publication (including tasks that weren't due to finish in this period).

Filter the Report

Export the Data

Changing the Published Version
Exporting as a CSV