Project Insight and the Power BI integration work alongside each other. Project Insight brings the most common performance reports directly inside Aphex, computed server-side, updated every publication. Power BI remains the best option for deeper, plan-level analysis.
These reporting needs are now available directly in Aphex. Where the same metric also appears in Power BI, the table notes it.
For the following, continue to use the Power BI integration:
Plan Comparison - compare the full plan between any two Published Versions at the task level. Useful for schedule audits and board reporting.
Publication Summary - readying completion, clashes, and blocker counts per user per publication. Useful for publication quality monitoring.
Resource actuals - Project Insight currently shows planned Labour, Plant, and Material only. Actuals (fed from the Site Diary) are coming next.
If you already have Power BI connected, these templates continue to work as before.
See also
PPC & Task Progress over time
PPC Dashboard
Yes (calendar-day basis)
PPC / Task Progress by Subcontractor & Owner
PPC Dashboard
Yes
Delay breakdown by reason, subcontractor & owner
Delay Breakdown
Partial
Milestone status & movement over time
Milestone Analysis
Yes (Variance template)
Planned Labour / Plant / Material demand
Resources
Yes