The Resource reports show planned Labour, Plant, and Material demand across your project, helping you anticipate peaks and plan ahead.
Each resource report has two widgets: a stacked bar chart of total planned quantity by date, and a summary table with the minimum, maximum, and total planned quantity per resource.
The bar chart shows demand across time, with each resource type represented by its own colour.
The summary pivot table shows Minimum, Maximum, and Total planned quantity per resource - expandable to see each individual task-day.
The date range defaults to today + 6 weeks.
Use the date range picker to focus on a specific window of time.
To change the date range:
Use the Date Range picker in the filter bar
Select a start and end date for the period you want to analyse
The chart and table will update to reflect your selection
Below the chart, the Summary table breaks down planned quantities per resource, with the option to expand each row to see the day-by-day detail.
Each resource appears as a collapsed row showing three values across your selected date range:
Minimum Planned Quantity - the lowest planned quantity on any single day
Maximum Planned Quantity - the highest planned quantity on any single day
Planned Quantity - the total planned quantity across the full date range
To see the day-by-day breakdown for a resource:
Click the > arrow next to any resource name to expand it
Each date row shows the planned quantity for that specific day
Narrow the report to show resource demand for a specific part of the project.
To filter resource reports:
Click Filters in the top right corner
Select one or more values. You can filter by: Task Owner, Subcontractor, Shift, Package, Assignee, Folder, Labour, Plant, and Material
Applied filters appear as removable tags; select Clear Filters to reset
To change which publication the report is anchored to:
Use the Publication selector in the filter bar
Defaults to the latest published version
See also
Every chart and table can be exported as a CSV, with your active filters applied. Read our doc for a step by step guide.