In Aphex, the projectβs WBS is built using Folders. Folders and Subfolders are how teams organise and group Tasks across the plan - whether you're pulling in a detailed structure from P6 or Asta, or building a more streamlined setup to suit daily and weekly site planning.
Root Folders sit at the top of your Folder hierarchy - everything else rolls up into them. You can create one directly from the Gantt while planning, or use the Folders Management page to build out your structure more intentionally.
Make sure that your set to Folders
An option to Add Root Folder will appear on the Gantt
Click your Project Title in the top left, then select Project Assets
Select Folders from the menu
Click
Add a Folder Name and update the code if needed
Subfolders help you build out your Folder Structure with as much detail as your plan needs. You can nest Subfolders as deep as required - there's no limit!
From the Folders Management Page:
Click your Project Title in the top left, then select Project Assets
Select Folders from the menu
Hover over the Folder you would like to add a Subfolder to
Click on the +
Hover over the Folder you are adding to
Click on the + symbol
Select Add Subfolder
Type in the Subfolder Name & select the Create [Folder Name]
If parts of your Folder Structure need to stay exactly as they are, you can apply Folder Protection. You can lock down changes to names, codes, position, or structure - including the ability to add Subfolders.
Click your Project Title in the top left, then select Project Assets
Select Folders from the menu
Locate the Folder you'd like to Protect
Click the in the State
Reordering Folders is quick and flexible. Move a single Folder or an entire branch - just remember that the Folder Structure is shared with everyone on the project, so your updates will apply project-wide.
Click your Project Title in the top left, then select Project Assets
Select Folders from the menu
Hover over the Folder name & click and hold to the left of the checkbox
Drag the Folder to move it
To move a Folder using the Overflow Menu
Hover over the Folder & click the ...
Select Move to bring up the menu
Click on the Folder you want to move to & confirm using the button
Click Save Changes
You can duplicate Folders to help build out your Folder Structure faster β avoiding the need to recreate similar setups manually.
From the Folders Management Page:
Click your Project Title in the top left, then select Project Assets
Select Folders from the menu
Hover over the Folder & click the ...
From the Gantt:
Locate the Folder(s) you want to duplicate.
Hover over the Folder & click the ...
Choose one of the two duplication options:
Duplicate β duplicates only the selected Folder and the tasks visible within it.
To use the Folder Importer, upload a spreadsheet with both a Code and Name for each Folder.
The importer works with CSVs exported from other planning tools. If your system doesnβt support folder exports, you can copy folder codes and names manually into our template.
Click your Project Title in the top left, then select Project Assets
Select Folders from the menu
Click
Choose either Upload a File
See also: import Folders from your
Folders can be deleted one by one or in bulk - whatever works best for your clean-up.
Click your Project Title in the top left, then select Project Assets
Select Folders from the menu
Hover over the Folder you wish to delete
Select ...
This organises your Tasks by the Folders they belong to. It's a simple way to view your plan in the same structure used across the Project.
Click the menu in the top left of the Gantt
Pick Folder as a Primary Grouping
Click the menu in the top left of the Gantt
Select the button next to Folder to switch to Flattened Folders
Flattened Folders shows only the lowest level Folder for each Task in a single row
Apply a Folders Filter to see only the Tasks sitting in certain parts of your Project structure.
Click and
Select Folder in the first dropdown
Select the Operator in the second dropdown
Is Within to reveal Tasks that sit inside the selected branch
See also: create & share
Click Save
The Folder is added to the project structure, ready for the team to add Tasks into
Select Add Sub-Folder
Add a Folder Name and update the code if needed
Click Save Changes
The Subfolder is added to the project structure, ready for the team to add Tasks into
Default
Semi-Protected
Protected
Click Save Changes
Click Save Changes
Duplicate β duplicates only the selected Folder.
Duplicate Branch β duplicates the Folder and all its Sub-Folders.
Click Save Changes
Duplicate Branch β duplicates the Folder, all its Sub-Folders, and the tasks visible within them.
Choose one of the two options in the Task Ownership Modal
Keep original Owners
Assign Ownership to me
Click Confirm Duplicate
Copy and PasteAdd your data (upload CSV or copy and paste)
Map both the Folder Code and Name fields
Review your data
Complete the Import
Delete FolderThe full Folder path appears above the Folder Name, saving vertical space
Click the same icon again to return to Folder Tree mode
Folder Tree shows your full Folder hierarchy, one row per level, so you can see exactly where each Tasks sits in the structure.
Is to reveal Tasks that belong to the specific Folder
Pick your Folders in the third dropdown
Click Apply Selected

1
Default
β
β
β
β
Semi-Protected
-
-
-
β
Protected
-
-
-
-
Admins & Members (Allow Root Folders: On)
Can duplicate any folder or branch.
Can duplicate any folder or branch.
Admins & Members (Allow Root Folders: Off)
Can duplicate any folder or branch.
Cannot duplicate root-level folders, but can duplicate any nested folders.
All duplication options are disabled.
Admins & Members (Allow Root Folders: On)
Can duplicate any folder or branch.
Can duplicate any folder or branch.
Admins & Members (Allow Root Folders: Off)
Can duplicate any folder or branch.
Cannot duplicate root-level folders, but can duplicate any nested folders.
Admin
All duplicated tasks will keep their original owners.
All duplicated tasks will be assigned to you.
Member (No Delegate Permissions)
Tasks owned by other users will be skipped and not duplicated.
All duplicated tasks will be assigned to you.
Member (With Delegate Permissions)
Tasks owned by other users will be skipped unless you have delegate permissions.
All duplicated tasks will be assigned to you.