Distributing Imported Work to the Team
You can import data into Aphex from your master schedule in .XML format.
Import Workflow
Starting an Import
You can access Imports using your sidebar.
From the Imports page, click the Import Data button to begin the simple 5-step Import workflow.
Step 1: Upload
Drag and drop or browse and upload your .XML file containing project data to be imported.
Step 2: Custom Filter (Optional)
If you decided to create a custom filter in your master schedule, select the user defined field and value from the two drop-down lists.

Step 3: Time-frame
With plans and site evolving every day, Aphex minimises potential divergence of plans by allowing a time range restricted dataset to be passed from master schedule to short-term plan.
Select a time-frame of data to import from 4 weeks, 12 weeks, All future and All past and future. You'll see how many activities exist within these time-frames on your .XML file.

Step 4: Map Fields (Optional)
Here you can select your master schedule Work Breakdown Structure to be imported and assigned to activities in your lookahead.
If you decided to enrich your master schedule with data to customise your import process, here you can select your custom Owner, Subcontractor and Location user defined fields from the drop-down lists to be mapped to imported activities.

Step 5: Review and Import
The final step of the import workflow displays a summary of new data generated by the import. The date range of new data, and the number of tasks, WBS Codes, Owners, Subcontractors, Locations and Calendars created.
Finalise the import by clicking Import Data.

Distributing Work to the Team
If work was not assigned to an owner in Step 4 of the import workflow, you will find all imported activities in your Unassigned section of Project Data.

Here work can be edited and assigned to its rightful Owner. You can assign in bulk using the check-boxes on the left of the table, you can multi-select by holding the SHIFT key.

Once assigned to the team, work will be found in each user's Backlog, ready to be brought into the plan.