For users wanting their Aphex WBS to follow an external Work Breakdown Structure, the WBS importer allows the WBS to be created from a CSV or any spreadsheet format.
💡 For projects Connecting their Master Schedule: remember that Master Schedule imports use the WBS Code property to map the WBS. |
Prepare your WBS Import
The WBS importer supports a simple CSV or table-formatted data structure. In order to create new WBS codes, the tool requires both a WBS Code and WBS Name to be assigned and mapped.
WBS Property | Format |
WBS Code | A period-separated code (sometimes called WBS path) Example; East.123.A.1 This would be imported as
|
WBS Name | Any String |
💡 The WBS importer will autocomplete WBS branches where they are missing in the source file. For example, a WBS Code imported as East.123.A.1 will automatically create the parent nodes of East, East.123, and East.123.A if they are not included in either the source file or the existing Aphex project. |
Formatting your WBS Import
The importer supports any CSV export from other planning tools. If your existing planning system does not support a WBS export, you can also copy the WBS code and name directly from the interface and paste it into our example CSV template below.
![]() | Downloadable resources: |
Running an Import
You can initiate an Import from the WBS page within your project in Aphex Planner.
Navigate to the WBS page
Select 'Import WBS'
Choose either 'Import from CSV' or 'Copy and Paste'
Add your data (upload CSV or copy and paste)
Map both the WBS Code and Name fields
Review your data
Complete the Import
💡 The WBS importer will automatically warn of and exclude any WBS codes that are duplicates of existing WBS codes in the import file or the existing Aphex project. |