Production Measures let you define the measurable outputs work is planned against, each created with a name, unit (e.g. ‘Panels, each’), and an optional target rate per day. When a target rate is set, Aphex calculates the implied daily rate and compares it against that target, surfacing the variance as a red, amber, or green indicator in a dedicated Production Measure column on the Gantt.


Creating Production resource lets you build a reusable library of Production to assign to Tasks.
Click your Project Title in the top left, then select Project Assets
Select Production from the menu
Click ![]()
Create your custom Production resource by entering the Name, Unit and a Colour
Optionally assign a Unit Name and toggle
Set Daily Target Rate
The Production resource is added to the library of Production the team can assign to their Tasks
The Unit is confirmed once a measure is created; name, colour and target rate can be edited. Percentage-based measures have no quantity, target or breakdown.
Choosing Count adds a custom Unit Name e.g. ‘Panels’.

Assign Production to tasks and track progress throughout the task duration
Assign from the Gantt column and the task side panel.
Pick a unit-based measure to open a planning view where you can set the total quantity, review the daily breakdown and alignment, then

Make changes to the production breakdown where needed and impact the cumulative total needed.
Right-click a Task and select View Details
Scroll to Planned Resources and click into
Update the value and see the cumulative total impact
A Task's Production breakdown is locked the moment the Task is Promised, or once it has any Progress recorded. Once Confirmed, the measure, quantity and breakdown becomes read-only. To change them, delete the task's progress first or change the status to Planned.
Unit-based measures (m³, linear metres, items, etc.) take a total quantity, support an optional daily target rate, and show a day-by-day breakdown with on/ over/ under targetstatus.

When a task's average production rate is below or in excess of its target, you can extend or shorten the task duration in one click so it lines up with the target rate no manual recalculating needed.
Hover the Target Rate Variance icon on the Production Gantt cell, in the Task side panel, or on a Board/List task card
Where the average is off target, an Align Task Duration button appears
Click it to extend or shorten the task duration until the daily average production matches the target rate
The quantity breakdown updates automatically to reflect the new duration

Once a Production Measure with a target rate is assigned to a task, Aphex continuously compares the task's planned daily rate against that target so misalignment is visible before it becomes a problem.
Resizing or dragging a task with a Production Measure assigned updates its plan in real time.
As you stretch or shrink the Task Bar, a Task Resize Indicator tooltip shows a live preview of the new average daily production rate
If the measure has a target rate set, the tooltip also shows whether that new average is aligned, above, or below target
Release the bar to confirm the new duration the daily breakdown recalculates automatically
On the Gantt, navigate to
and toggle on
Production
Check the visuals of ,
and
to check the Target Rate Variance
Over the current target rate and could mean reforecasting is needed

Click and
Select Production in the first dropdown
Select from Is, Is Not, Is Empty or Is Not Empty in the second dropdown
Select your desired Production measure in the third dropdown
See also: create & share Views
On the current Target and is in accordance with the daily forecast rate
Under the current target and could mean the duration of the task can be shortened
Multi-Select