This guide outlines how to prepare your Asta Powerproject file before importing into Aphex. We've included known quirks, export tips, supported file types and small adjustments that can make a big difference once the file is uploaded into your Aphex Project.
Once you've exported your file, see how to run the import into Aphex: Master Schedule Import
XER
XML (Primavera P6 Schema)
XML ( Microsoft Project Schema)
MPP
Visit the Asta Documentation for guidance on how to export to &
Often, your delivery team won't need to see every single task in the Master Schedule in Aphex - they just need the right slice of it. Filtering before you export from Asta means the plan you import into Aphex includes only relevant tasks, not cluttered with everything else, like Procurement or Design. There are three main ways to filter, let's take a look at each below.
Best For: Quick exports of exactly what’s on screen
Supported Export Formats: MS Project XML or MPP
For full details, visit the Asta Documentation to see how to and learn more about the
Best For: Selecting a complete phase/area/discipline directly from the WBS (one or several branches) and bringing it across intact.
Supported Exported Formats: MS Project XML or MPP
For full details, visit the Asta Documentation for
Best For: Granular control over exactly which tasks you want to import, regardless of where they sit in the overall structure.
Supported Exported Formats: MS Project XML, MPP, P6 XML, XER
For full details, visit the Asta Documentation to see how to work with
See also: apply your Custom Filter during the
Aphex can build your folder structure from your Asta hierarchy. It only creates Folders for WBS levels that have Tasks included in your import (empty branches aren’t created).
Your mapping options depend on the export schema you’re using:.
What it is: The formal WBS code in the exported file
Why pick this: You want folders to follow the project’s formal WBS exactly. Only select this option if you’ve built/assigned WBS codes to activities
Supports: Primavera P6 XML and XER
What it is: A hierarchy built from the chart/summary grouping at export time (the “natural” on-screen order)
Why pick this: You want Folders to mirror the practical on-screen grouping you used when exporting. Select this option when you’re organising by visible grouping and don’t have WBS codes in place.
Supports: Primavera P6 XML and XER
What it is: An automatic path like 1.2.3 that shows a task’s exact position in the outline
Why pick this: You want Folders to mirror the on-screen outline from an MS Project-schema export
Supports: MS Project XML and MPP
What is it: Asta’s Work Breakdown Number assigned to each task. It’s a hierarchical, generated identifier (often looks like 1.2.3). It isn’t the formal WBS code; it’s Asta’s task ID scheme
Why pick this: If your team already references WBNs and wants that familiar structure reflected in Aphex
Supports: MS Project XML
By default, Aphex imports all core task & relationship data from your export.
If you've already captured extra information in Asta, like Owner, Location, Subcontractor or Notes, you can pull these into Aphex too, using Asta's Task-level User Fields.
If you don't - that's no problem! It's easy and quick to apply the same edits in the Aphex plan.
Create a User Field in Asta:
Select Task in the Object type dropdown
Choose String as the
Repeat for any other optional property you want to import.
Also: How to map User Fields during the
Asta’s Summary Bars are used to group and structure Tasks in a hierarchical plan. In Asta, they’re a distinct Object Type.
However, when imported into Aphex, Summary Bars are treated as regular Tasks, which can result in duplication if the Tasks they summarise are also imported.
Mid‑Links are a type of logic link in Asta where the dependency connects to or from the middle of an activity, rather than the start or finish.
To keep things as simple as possible for end users, Aphex doesn’t handle mid‑link logic - all links must connect to either the start or end of a task.
Additionally, as mid-links aren’t supported in P6 or MS Project, Asta converts them during export to XML or XER to the closest matching link type.
In Aphex, the smallest possible task duration is one day.
This works well once tasks are in Aphex, but it can cause changes if you’re importing from a Master Schedule where some tasks are shorter than a full day.
Aphex automatically handles these adjustments during the import process, which should result in sequenced tasks remaining aligned on the correct dates, without you needing to do anything.
To keep Aphex as simple as possible, constraints are not supported (e.g., “Must Start On”, “Start No Earlier Than”). When you import from Asta, Aphex will schedule from links, durations, start date and calendars. As a result, tasks that were being “held” by constraints in the source file can move once imported and be a source of variance.
Aphex assumes the lookahead inside Aphex is most up-to-date version of the plan, once tasks are imported. On later imports, existing Aphex tasks are not overwritten. Imports only ever create new tasks (i.e., tasks that don’t already exist in Aphex).
Often, your Master Schedule is contractual, so nothing should change by accident. Aphex shows what’s moved and why; updates back to Asta stay manual, deliberate, and on your terms.
Weekly Published Versions & Import Baselines - snapshots you can compare against.
Variance Reports & Exports - quickly see what changed since the last baseline (date moves, duration changes, new/removed tasks, completion).
Field typeWe've suggest naming it something descriptive, like Aphex_Subcontractor
Add this new User Field as a column in your Asta view
For each Task you're importing, add in the value (the Subcontractor name, in this example) in the relevant cell
External ID awareness - imported tasks carry the Asta identity, even when imported Tasks have been broken down into subtasks, so you can still line them up 1:1 when editing in Asta.Open your programme in Asta
Build a filter to show just the tasks you want (for example, construction activities, a specific date range etc).
In Asta: View → Filters → New Filter
Apply the filter so your view shows only those tasks
Right-click anywhere in the project view (or on a summary group) and select:
Export branch or view to Microsoft Project
Choose MS Project XML as the export format.
In the export wizard, look for the option:
Export only visible tasks or “Export current view
Confirm the export - only the tasks visible in the filtered view will be included in the file.
In Asta Powerproject, expand the WBS so you can see the branch (summary group) you want to export
Select the WBS branch. To export more than one, hold CTRL and click additional branches
Right-click the branch and choose:
Export branch or view to Microsoft Project.
In the Export dialog, select Branch
This ensures only the chosen WBS branch (or branches) will be included
Confirm Microsoft Project XML as the export format
In Asta, create a new User Field:
Project → Properties → User-Defined Fields
Type: Task
Data type: String
Suggested name: Aphex_Import
Tag tasks to import
Set Aphex_Import = Yes on every task you want to bring into Aphex.
Export the project
Use your required schema: MS Project XML, MPP, Primavera P6 XML, or XER
In Asta, Tasks and Milestones are treated as separate object types. If you create a User Field for the Task object, it won’t be applied to Milestones - even if they appear in the same activity list.
This means that if you're filtering for Milestones alongside Tasks, as the User Field you’ve created is Type = Task and Data type = String, it won’t apply to Milestones - so they won’t pass the "Aphex_Import = Yes" filter during import.
In Asta, export to Microsoft Project XML
Whole project: File → Import/Export → Export to Microsoft Project
→ during the Map Fields step:
Map Folders = Task ID (WBN)
There’s no additional checkbox to 'include WBN' - if WBN codes exist in your project, Asta writes them into the MS Project XML and Aphex will expose them as Task ID (WBN) during mapping.
Visit the for more detail
For full details on creating and managing User Fields, visit the Asta Powerproject documentation.
Subcontractor
Subcontractor Name
For Subcontractor and Location, insert the value for each relevant activity.
If the value already exists in your Aphex Project, the imported Tasks will automatically be assigned to the relevant Subcontractor or Location
If the value is unique, Aphex will create a new Subcontractor or Location and assign the imported tasks to the newly created asset
In Asta, Tasks and Milestones are treated as separate object types. If you create a User Field (UF) for the Task object, it won’t be applied to Milestones - even if they appear in the same activity list.
This means that if you're importing Milestones alongside Tasks, any values for optional fields like Subcontractor, Owner, Location, or Notes won’t carry over for Milestones. You can still add them manually in Aphex after the import.
If Summary Bars are used purely for grouping, consider filtering them out before export to avoid duplicating detail tasks.
Alternatively, if you’re looking to bring in a high-level version of the programme, you can choose to import just the Summary Bars for a top-line plan.
There's no perfect fix for mid-links, since Aphex doesn't support them, and by the time your file reaches us, Asta has already converted them to standard logic links. Here are a few ways you can approach this:
Review mid-links before exporting
If there are only a few, it might be worth replacing them with simpler link types, or removing them if they're not essential
Export a logic free version
If you have prolific use of mid-links, you might explore exporting a copy of the file with no dependencies at all. This avoids misinterpreted links entirely, and will ensure that all imported activities land on their correct dates. This could be a good option to consider if you're only bringing in high-level activities that the team will be breaking down and detailing anyway, or just the key milestones that they can build towards
Be ready for some variance
If mid-links stay in, expect some differences in how tasks relate to each other in Aphex
Every task is rounded up to a minimum of one full day
E.g a Task that was 3 hours becomes 1 day.
A Task that started at 9pm and finished at 9am becomes two full days
We add -1 day lag to successor logic links to offset the extra time
E.g if you had three 1 hour tasks linked in a F>S chain all happening on the same day, we automatically convert them each to 1 day tasks, and subtract one day of lag from each relationship.
This keeps all tasks starting on the same day, matching your Master Schedule, while still meeting our minimum duration requirement
Aphex matches “same task as before” using the External ID which is automatically mapped during import:
Primavera P6 XML / XER: maps External ID = Activity ID
MS Project XML / MPP: maps External ID = <projectname>_<taskUniqueId>
<projectname> is the name of the MS Project file
(WBN / OutlineNumber / WBS Code / Natural Order control folder structure, not Task identity.)
Rule: if the External ID in the incoming file matches an Aphex task’s External ID, Aphex treats it as “already imported” and does not update it.
From the Gantt: Baseline Overlay Task Data Export
From Power BI: Connect to Power BI Plan Comparison Dashboard
From Aphex Insight: View the Variance Report and Download the Variance CSV
Make sure this is selected - otherwise, Asta will export the entire schedule.
User‑Defined Fields are includedFor Owner, insert the email address of the activity’s owner.
Check that this matches the email address the team member uses for Aphex. This will ensure the Tasks are automatically assigned to the correct user.
If not, the address entered will receive an invite to join the Aphex project.
For Notes, they will automatically be added as a text note to the specific imported activity
<taskUniqueId> is the unique task ID from the file
E.g. if you have a task with ID 123 in a file called "aphex-program-2.0", the External ID would be aphex-program-2.0_123.
Cannot export filtered view
MPP and XML (MS Project Schema)
Exporting specific branches
Exporting filtered views
Using WBN or OutlineNumber
Repeating imports over time is harder if the Asta project name changes, as it affects task identifiers and can cause duplicates
Aphex_Subcontractor
Owner
Owner's Aphex Email Address
Aphex_Owner
Location
Location Name
Aphex_Location
Notes
Free Text
Aphex_Notes