Board

Who can use this feature?

Project Users with Full Planner Access can create and open Board Views.

Board View gives you a whiteboard-style layout of your plan, powered by your lookahead. Drag and drop Tasks, record progress, and adjust your plan as work progresses - all changes update instantly across your schedule.

Setting Your Date Range


The date picker lets you choose how many weeks to display on the board, from one week up to four.

To set a date range:

  • Click the date range

  • Select your preferred range at the top of the picker: 1 week, 2 week, 3 week or 4 week

  • Click any start date in the calendar, the end date calculates automatically

Multiple weeks Logic & Rules

  • Ranges span forward from the date you click, you only need to select a start date

  • Mid-week selections are supported (e.g., Wednesday to Wednesday)

  • Ranges shorter than one week are not supported

  • Your last selected range length is remembered across sessions

Navigating the Board


Use the arrow controls, zoom slider and scrubber to move through your timeline and adjust how much of your plan is visible at once

To change the Timeframe :

  • Click to move forward or backward by one week

  • Click to jump to the current period

Zoom

  • Shows one week in detail

  • Shows two weeks for a broader view

Scrubber

  • The highlighted shows what’s currently visible

  • Drag the highlighted section to move through your plan

Navigation Logic & Rules

  • Click and drag anywhere on the board to pan

  • Hold Shift and use your mouse wheel to scroll horizontally

  • Both the zoom control and scrubber are hidden when your date range is set to 1 week only

How Tasks are Grouped


Board Views can be organised into different swim lanes, depending on what type of set up you need.

To change the Grouping:

  • Click at the top of the Board View

  • Select how you want to group tasks

  • Use ⋮⋮ to drag your Groups in the order in which you want them to be displayed

  • Tasks and Groups will reorganise automatically

Grouping Options
Primary Group
Sub-Group

Owner

Folder

Package

Owner

Folder

Subcontractor

Subcontractor

Shift

Shift

Location

Location

Assignee

Assignee

None

Create & Edit Tasks


To create a Task on Board:

  • Click the in the bottom left-hand corner

  • Complete the Task details

  • Click to add it to the plan

Tasks created from the Board use your current view to pre-fill details like Group and date.

To edit a Task on Board:

  • Click on any visible Task Property

  • Select a new value

  • Changes are saved automatically

Moving Tasks


To drag and drop Tasks on Board:

  • Change dates: Drag to a different day

  • Reorder: Drag up or down within a Group

  • Reassign: Drag between Groups

Reordering Tasks

Tasks on the Board will always be sorted by Start Date - the earlier a Task starts, the higher it will appear within it's grouping.

Aphex will hold the position of your Tasks while you make edits, and then when you're ready to re-apply the Sort Order, click in the bottom right corner.

Refreshing your Aphex window will also trigger the sort order to be re-applied to your Board View.

Moving Tasks Logic & Rules

  • The Task stays exactly where you place it

  • Tasks will not automatically reorder after being moved unless tidy up has been clicked

Recording Task Progress


Use Board to record how each day went and keep your plan up to date. Every update feeds into reporting and the wider schedule, with changes reflected instantly across all other Views.

To record a Delay or Improvement:

  • Open and toggle Progress

  • Click the progress bar on the day you want to log an update

  • Choose to mark it on track or improved, or to record a delay

  • The progress bar will turn green or red based on the update type

See also: Progress Updates

Monitor Daily Task Progress


See at a glance how many of your Tasks have been updated each day, with a live breakdown of what's on schedule, delayed or missing an update.

  • Click

  • Toggle Show Task Update Compliance

  • Click , or to filter to just that day

  • Optionally, click to show all missing updates of tasks today/past within the view

  • Click to dismiss

Task Update Compliance Logic & Rules
  • Toggling on Task Update Compliance is per-user and won't affect anyone else's view

  • Compliance counts update in real time

  • Only Tasks visible in your current view and date range are counted

  • If a Task is assigned to multiple people and appears in multiple Groups, it's only counted once

Filtering the Board


Filters in Aphex let you show only what matters, whether that’s Tasks with certain properties, or ones that are missing something. Keep it simple or build something more detailed, it's up to you.

To filter a Board View:

  • Click at the top of the Board

  • In the dropdown that appears select and choose the property you'd like to filter by

  • Change the logic from options like or to or to hide or reveal the relevant Tasks

  • Click to swap between and

See also: creating & sharing Views

Filter Logic & Rules
  • All Task Properties as well as Unresolved Issues can be applied as a filter

  • Archived values that are still in use will appear as filter options. Unused archived values will be hidden from the filter options

  • Tasks that do not match the filter criteria will be hidden from the Board

Customise Task Properties


Tailor your Board View to suit the way you plan & communicate. Adjust the layout, colour coding, visible days of the week and more.

To hide or reveal properties:

  • Click at the top left of the Board

  • Toggle any property you'd like to display on the Task Cards

  • Use the ⋮⋮ drag handles to reorder the properties on the Task Cards

  • Optionally, click the > beside the property to open more options

  • Use the to hide specific values within that property from view

Customise the Board Layout


To change the visible days:

  • Click

  • Select Days

  • Pick from 5 Day, 6 Day or 7 Day

To switch the Board Layout:

  • Click

  • Select Layout

  • Pick between Waterfall or Masonry

To colour code Task Cards on Board:

  • Click

  • Select Card Colour

  • Pick from Owner, Subcontractor or Shift

Board View Options
Colour
Description

Subcontractor

The colour of the Tasks allocated Subcontractor

Shift

The colour of the Task Shift

Owner

The user colour of the Task Owner

  • Relationship links can also be hidden or displayed by toggling the property on and off in the View Options menu.

    • Relationship links will be turned off when grouping by assignee.

See also: Print Board