Exports

Who can use this feature? All Project users can export Project data.

Exporting lets you download key project data from live plans and published versions to Resources, Folders, Blockers, and Milestones.

Exporting Live Plans


You can export your live plan from the Gantt, Map, Board, or List views. The export will reflect whatever filters and dates you’ve set at the time.

To export a Live plan:

  • Open your preferred view and click

  • Select

Exporting Live Plans Rules
  • Data included in the file is defined by the Filters and Dates set at the time of the export.

  • The export includes three files: one for Tasks, one for Progress Updates and one for Folders

Exporting Published Versions


Exporting a published version lets you download plan data exactly as it was at the moment it was published. The export will reflect whatever filters and dates you’ve set at the time.

To export a Published version of a plan:

  • Open any Published version and Click

  • Select Export Tasks to CSV

See also:


Export the Resource Overlay to get a daily breakdown of Labour, Plant, Materials, or Subcontractors based on your current view and filters.

To export Resources:

  • Navigate to the Gantt view and select

  • Click and select the desired resource

  • Select and click

See also:


Exporting a project’s folder structure creates a CSV file with each Folder’s name and code, making it easy to review or reuse your Folder setup.

To export Folders:

  • Click your project title in the top left

  • Select Project Assets

  • Open the Folders page from the menu

See also:


You can export Blockers from the live Gantt, and the file will match whatever filters and dates you’ve set at the time.

To export Blockers:

  • Navigate to the right-side of the Gantt and click

  • Click the configuration icon and select

See also:


You can export Milestones from the live Gantt, and the export will reflect the filters and date range you’ve set at the time.

To export Milestones:

  • Navigate to the right-side of the Gantt and click

  • Click the configuration icon and click

See also:


You can export Clashes from the live Gantt and Map, and the export will reflect the filters and date range you’ve set at the time.

To export:

  • Navigate to the right-side and click

  • Click in the top-right of the Clashing Tasks panel

  • Click

See also:

Select
For tasks without a Production Measure,
Production
is left blank.
Production % Complete
is filled in when the project is set to
Track % Complete
and progress has been logged.
Exporting Published Versions Rules
  • Data included in the file is defined by the Filters and Dates set at the time of the export.

  • The export includes three files: one for Tasks, one for Progress Updates and one for Folders

  • For tasks without a Production Measure, Production is left blank. Production % Complete is filled in when the project is set to Track % Complete and progress has been logged.

Exporting Resources

Resource Utilisation Tool
Option
Meaning

Total Task Utilisation

The number of Tasks that have the Resource assigned per day

Exporting Resources Rules
  • Data included in the file is defined by the Filters and Dates set at the time of the export.

  • The export includes two files: one for Total Task Utilisation and one for Total Project utilisation.

Exporting Folders

Exporting Folders Rules
  • A Folders CSV will be downloaded

Exporting Blockers

Exporting Blockers rules
  • Data included in the file is defined by the Filters and Dates set at the time of the export.

  • A Blockers CSV is downloaded

Exporting Milestones

Exporting Milestones Rules
  • Data included in the file is defined by the Filters and Dates set at the time of the export.

  • A Milestone CSV is downloaded

Exporting Clashes

Exporting Clashes rules
  • A ZIP file downloads containing three CSVs, one for each tab

  • All active filter values are applied consistently across all three files

  • If a Task clashes with multiple other Tasks, it appears on a separate row for each clash partner

  • For Non-Conflicting rows, Overlap Start, Overlap End and Overlap Duration are left blank

  • Group By and Overlay Property are UI-only and do not affect the CSV structure

  • Each CSV includes: Task Name, Activity ID, External ID, Owner, Owner Email, Start Date, End Date, Duration, Location, Folder, Subcontractor, and the matching fields for the clashing Task, plus Clash Status, Overlap Start, Overlap End and Overlap Duration.

Publishing
Resource Overlay
Folders
Blockers
Milestones
Clashes

Total Project Utilisation

The daily allocation of the Resource