Materials can be added to Tasks to forecast your daily resource demand and track planned vs actual quantities.

## Creating Materials

***

Creating Materials lets you build a reusable library of Materials to assign to Tasks.

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2F4OTzASb3pZTxSc3WPrNE%2FCreate%20Material.svg?alt=media&#x26;token=c20196c1-724f-48b3-aa72-d5cb36639d47" alt=""><figcaption></figcaption></figure>

**Creating New Materials:**

* Click your Project Title in the top left, then select  `Project Assets`&#x20;
* Select `Materials` from the menu
* &#x20;click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FjiyuWLAip5lvCBdzHSjI%2FButton%20(1).svg?alt=media&#x26;token=fef806cf-da8a-4cb5-98df-28a3d739e5f0" alt="" data-size="line">
* Create your custom Material resource by entering the name, unit, Material type and colour
* The Material is added to the library of Materials the team can assign to their Tasks

<details>

<summary>Material Type </summary>

Each material needs a Material Type from one of the following categories:

| Material Type |
| ------------- |
| Concreate     |
| Piles         |
| Earthworks    |
| Roadworks     |
| Electrical    |
| Drainage      |
| Steel         |
| Other         |

</details>

<details>

<summary>Material Unit</summary>

Each material needs a Material Unit from one of the following categories:

| Material Unit  |
| -------------- |
| Item           |
| Metres         |
| Metres Squared |
| Metres Cubic   |
| Kilometers     |
| Kilograms      |
| Tonnes         |
| Tons           |
| Yards          |
| Yards Squared  |
| Yards Cubic    |

</details>

## Assigning Materials&#x20;

***

Assigning Materials to tasks helps plan how much is needed for each one, making it easier to manage demand across your project.

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FFcWkqOtUuyfII0LemJyH%2FGantt-%20Material%20(1).svg?alt=media&#x26;token=8197ab9d-ba13-4641-b091-26f2f54cc423" alt=""><figcaption></figcaption></figure>

**To add Planned Materials to a task:**

* On the Gantt, navigate to the column picker <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FfcDCzafJHCtgSfMJuQOz%2FIcon%20Buttons%20(1).svg?alt=media&#x26;token=08227bc3-6692-4d7e-818b-295f7a9cf16f" alt="" data-size="line"> and toggle <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FrvTcctNRDtoOHaw7U9zU%2FTheme%3DLight%2C%20Size%3DRegular%2C%20State%3DOn.svg?alt=media&#x26;token=d08029bc-cd20-4401-bc69-8ded58cdca38" alt="" data-size="line"> `Materials`
* Click the Material cell for your task & select Materials from the dropdown menu

See also: <a href="../tasks#editing-tasks" class="button secondary">Bulk Edits</a>

<details>

<summary>Material Property Rules </summary>

* Materials are a multi-select property
* A Quantity of the Material can be inputted when adding Materials to tasks
* Quantities are applied per day
  * The unit quantity is split across the task's duration
* Archived Material resources will no longer be available to add to tasks but will still exist on tasks it was assigned to before the resource was archived

</details>

## Editing Planned Daily Quantities&#x20;

***

When you add a planned Material, Aphex spreads the total amount across the Task’s planned days. If you expect to use more or less of a material on a certain day, you can adjust the daily quantity to match.

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FO2VhbbHDfRr1WObZuaIG%2FMaterials%20-%20Planned.svg?alt=media&#x26;token=69303eca-3984-49c6-91f6-027667ddeea1" alt=""><figcaption></figcaption></figure>

#### To adjust the daily planned quantities:

* Double-click your task bar on the Gantt to open the right-hand panel
* Scroll down to `Planned Resources` and click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2F2ww29X4huVUxXaygDvFh%2FIcon%20Buttons%201.svg?alt=media&#x26;token=a30a6b6b-7849-488c-9b54-28be4252dd3c" alt="" data-size="line"> to expand your chosen Material
* Click into the Quantity box and change the value&#x20;

## Material Actuals&#x20;

***

Material tracking doesn't just stop at forecasting demand. Use Actuals to log what was used each day, directly on the Task - giving you a clear picture of performance over time, and use the inputs to automatically generate planned vs actual quantity reports.&#x20;

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FT6rofUDFnt5pZ4E65aZG%2FMaterials%20-%20Actuals.svg?alt=media&#x26;token=bcc6c0f2-ff77-4a9c-8a67-cb7bbd06df73" alt=""><figcaption></figcaption></figure>

**Adding Actuals to Tasks:**

* Double-click your task bar on the Gantt to open the right-hand panel
* Scroll down to `Actual Materials` and click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2F2ww29X4huVUxXaygDvFh%2FIcon%20Buttons%201.svg?alt=media&#x26;token=a30a6b6b-7849-488c-9b54-28be4252dd3c" alt="" data-size="line"> to expand your chosen Material
* Click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FsM2paq0YxhwqYWdshWUR%2FText%20Buttons%20(6)%201.svg?alt=media&#x26;token=68fe97cb-b889-4f20-840e-199893fa935a" alt="" data-size="line">and select a planned material&#x20;
* Pick a day to record the Actual against, enter the Quantity and click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FmR6cEQh6zVAxbVqavdKl%2FIcon%20Buttons%20(1).svg?alt=media&#x26;token=b206e05d-2a34-4e9b-ad0a-6cdd773d99da" alt="" data-size="original"> to confirm

## View Forecasted Materials on the Gantt

***

Use the Resource Overlay in the Gantt to forecast Material demand day by day. You'll see how much of each Material is needed across the project, with a clear breakdown of which Tasks are driving that usage and who's using it.&#x20;

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2F5QMkT6jJ5WTuJxkHVtvy%2FResource%20overlay%20-%20Material%20(4).svg?alt=media&#x26;token=67479d0a-343b-41bb-a75a-aab932821824" alt=""><figcaption></figcaption></figure>

**View the Resource Overlay by Material:**

* Click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2Fght2Ug6Fnh80JV9rDzKs%2FSub%20Nav%20Buttons.svg?alt=media&#x26;token=680e7e22-ba8e-4a33-9280-3e0206fa97f0" alt="" data-size="line"> and select `Resources` and click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FOQWEkH3hyd6p1iibQvgr%2FMaterials.svg?alt=media&#x26;token=93ee3761-56b0-4188-b864-288c43624401" alt="" data-size="line"> Material
* Hover over the numbers to view your `Total` and `Project Utilisation`
* Click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FPt43XTI2R7SxDRvYVF1y%2FText%20Buttons%20-%20Work%20In%20Progress.svg?alt=media&#x26;token=5daae77a-8784-4d3b-85a6-36b5af6ccb6d" alt="" data-size="line"> to filter to a specific Material type
* Click the Resources Configuration icon <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2F7FmfgbVCzFvy29v6OYGm%2FIcon%20Buttons%20from%20Figma.svg?alt=media&#x26;token=d94cee5c-fed3-4842-aff9-b56b298b1ef8" alt="" data-size="line"> to switch between `Tasks in View` and `Project Utilisation`
* Hover over <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2F9D1l2IvdqWBj57q8lUGG%2F01%20Normal.svg?alt=media&#x26;token=00daf3e1-b03f-4b53-a171-cb2233e9c9ab" alt="" data-size="line"> to see the daily breakdown

See also: <a href="../imports-and-exports#exporting-resources" class="button secondary">Export Material Demand</a>

<details>

<summary>What's Shown on Hover</summary>

On hover, the daily breakdown includes:

* **Utilisation**
  * Quantity of Material used by Tasks in your current View (respects filters)
* &#x20;**# of Tasks**
  * Number of Tasks in your current View using that Material on the selected day (respects filters)
* **Project** **Utilisation**
  * Total quantity used across the entire project (ignores filters)
* **# no of Project Tasks**
  * Number of Project-wide Tasks using that material on the selected day (ignores filters)
* **Task Owner Breakdown**
  * Lists each Task Owner contributing to Project usage&#x20;
  * Includes Task Count and percentage of total utilisation for that day and Material&#x20;
* **Cell shading**
  * **Darker = higher quantity**
  * Lighter - lower quantity
  * Scale is relative to the values shown in the current overlay
* **Quantity values** are only shown in Day View
  * In Week, Month or Year mode, cell shading remains but numeric values are hidden

</details>

<details>

<summary>Resource Overlay Configuration Options </summary>

| Option                         | Function                                                                   |
| ------------------------------ | -------------------------------------------------------------------------- |
| **Total**                      | The demand for tasks in your current view                                  |
| **Project Utilisation**        | The demand for your entire project                                         |
| **Hide Un-utilised resources** | Removes resources that aren’t assigned to any Tasks from the resource list |

</details>

## Filter by Material&#x20;

***

Filter by Material to quickly review and manage work related to a particular Material items across your plan.

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FUrZOgDkPYDg8eLA91Z79%2FFilted%20by%20Material%201%20(3).svg?alt=media&#x26;token=5abeea80-2de8-4de2-baf3-85590df27285" alt=""><figcaption></figcaption></figure>

#### Filter by Material:

* Click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2F1uSzhSb5aSNnZd5vTaGB%2FFilter%20Button.svg?alt=media&#x26;token=8ddd7f1c-0296-4af2-bdeb-d08d56fc56b6" alt="" data-size="line"> and <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FbVv9qtyepRHQfkVwypud%2FText%20Buttons%20(2).svg?alt=media&#x26;token=fce29edb-8b74-4d75-bfa0-d8ad7292c94b" alt="" data-size="line">
* Select `Material` in the first dropdown
* Select from `Is`, `Is Not`, `Is Empty` or `Is Not Empty` in the second dropdown
* Select your desired Material item in the third dropdown

See also: create & share <a href="view-controls" class="button secondary">Views</a>

<details>

<summary>Filter Breakdown</summary>

| Filter   | Operator                                           | Value                          |
| -------- | -------------------------------------------------- | ------------------------------ |
| Material | <p>Is <br>Is Not <br>Is Empty <br>Is Not Empty</p> | <p>Multi-Select</p><p><br></p> |

</details>

## Report on Planned vs Actual Material

***

Once Materials have been assigned to Tasks, all updates (including Delays, On Track & Improvement events) can be traced back to each Subcontractor. This makes it easy to understand how each Subcontractor is performing across the project.

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FoBceT6OhZoH3Mv3MhFtI%2FMaterial%20-%20Insight.svg?alt=media&#x26;token=6daafb0b-0489-42fa-bff7-41d3804db4c7" alt=""><figcaption></figcaption></figure>

#### Power BI

Connect your Project as a datasource for Power BI to report on Material Demand, and track Planned vs Actuals.

#### Aphex Insight&#x20;

Utilise Aphex Insight to track Material Demand. See trends and drill down into specific Tasks to identify where each Material Resource is allocated.

See also: <a href="../../integrations-and-api/power-bi/getting-started-with-power-bi-reporting" class="button secondary">Connect to Power BI</a>