# Board

{% hint style="info" %}
**Who can use this feature?**

Project Users with Full Planner Access can create and open Board Views.
{% endhint %}

Board View gives you a whiteboard-style layout of your plan, powered by your lookahead. Drag and drop Tasks, record progress, and adjust your plan as work progresses - all changes update instantly across your schedule.

## Setting Your Date Range

***

The date picker lets you choose how many weeks to display on the board, from one week up to four.

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FVsK0ddRbx8siuM22bOIf%2FGroup%201321314343.svg?alt=media&amp;token=be769e07-24f6-44af-90a3-aba12cd993b2" alt=""><figcaption></figcaption></figure>

#### **To set a date range:**

* Click the date range
* Select your preferred range at the top of the picker: `1 week`, `2 week`, `3 week` or `4 week`
* Click any start date in the calendar, the end date calculates automatically

<details>

<summary>Multiple weeks Logic &#x26; Rules</summary>

* Ranges span **forward** from the date you click, you only need to select a start date
* Mid-week selections are supported (e.g., Wednesday to Wednesday)
* Ranges shorter than one week are not supported
* Your last selected range length is remembered across sessions

</details>

## Navigating the Board

***

Use the arrow controls, zoom slider and scrubber to move through your timeline and adjust how much of your plan is visible at once

#### To change the Timeframe :

* Click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FoiWNoBBjS7GP9j8J33yb%2FButton%20(4).png?alt=media&amp;token=81314536-7e82-44ad-b1ea-f89df01333a0" alt="" data-size="line"> <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FP0zae5ga93JJ2J7VlCE6%2FButton%20(3).png?alt=media&amp;token=45ac8c9d-805f-4a6f-a6ba-2706748ab4f6" alt="" data-size="line"> to move forward or backward by one week
* Click `Today` to jump to the current period

#### **Zoom**

* <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FRLEz2Cj6DTfCYnJnZSSD%2F_atomic_zoom.png?alt=media&amp;token=89632523-35f5-41bd-aff4-6d4be8039c98" alt="" data-size="line"> Shows one week in detail
* <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FrSfGkT6EWzg9NHhwJEfz%2FZoom%3DOut%20(1).png?alt=media&amp;token=704dfd89-6952-44d3-9bf5-a777c92aa378" alt="" data-size="line"> Shows two weeks for a broader view

#### Scrubber

* The highlighted <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FUiUO1vEALwWSbZUJ2GLd%2F_atomic_scrubber.png?alt=media&amp;token=e11f66ab-9e2d-42c0-a82b-c02e01d427d7" alt="" data-size="line"> shows what’s currently visible
* Drag the highlighted section to move through your plan

<details>

<summary>Navigation Logic &#x26; Rules</summary>

* Click and drag anywhere on the board to pan
* Hold Shift and use your mouse wheel to scroll horizontally
* Both the zoom control and scrubber are hidden when your date range is set to 1 week only
*

</details>

## How Tasks are Grouped

***

Board Views can be organised into different swim lanes, depending on what type of set up you need.

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FhXhCZzDmDV5YfR0OX6mW%2FTask%20Properties%20V2.png?alt=media&amp;token=d1f895f2-b3ce-48ba-a494-4a0e70f26420" alt=""><figcaption></figcaption></figure>

#### To change the Grouping:

* Click `Grouped by` at the top of the Board View
* Select how you want to group tasks
* Use **`⋮⋮`** to drag your Groups in the order in which you want them to be displayed
* Tasks and Groups will reorganise automatically

<details>

<summary>Grouping Options</summary>

| Primary Group | Sub-Group     |
| ------------- | ------------- |
| Owner         | Folder        |
| Package       | Owner         |
| Folder        | Subcontractor |
| Subcontractor | Shift         |
| Shift         | Location      |
| Location      | Assignee      |
| Assignee      | None          |

</details>

## Create & Edit Tasks

***

#### To create a Task on Board:

* Click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FwFFrr3TRxfuHoK1sgTAJ%2FFAB.png?alt=media&amp;token=6374eba4-7bfc-44cb-a161-f0bb8093d343" alt="" data-size="line"> the in the bottom left-hand corner
* Complete the Task details
* Click <kbd>Save</kbd> to add it to the plan

Tasks created from the Board use your current view to pre-fill details like Group and date.

#### To edit a Task on Board:

* Click on any visible Task Property
* Select a new value
* Changes are saved automatically

## Moving Tasks

***

#### To drag and drop Tasks on Board:

* Change dates: Drag to a different day
* Reorder: Drag up or down within a Group
* Reassign: Drag between Groups

#### Reordering Tasks

Tasks on the Board will always be sorted by Start Date - the earlier a Task starts, the higher it will appear within it's grouping.

Aphex will hold the position of your Tasks while you make edits, and then when you're ready to re-apply the Sort Order, click <kbd>Tidy Up</kbd> in the bottom right corner.

Refreshing your Aphex window will also trigger the sort order to be re-applied to your Board View.

<details>

<summary>Moving Tasks Logic &#x26; Rules</summary>

* The Task stays exactly where you place it
* Tasks will not automatically reorder after being moved unless tidy up has been clicked

</details>

## Recording Task Progress

***

Use Board to record how each day went and keep your plan up to date. Every update feeds into reporting and the wider schedule, with changes reflected instantly across all other Views.

#### To record a Delay or Improvement:

* Open <kbd>Layout & Properties</kbd> and toggle <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FrvTcctNRDtoOHaw7U9zU%2FTheme%3DLight%2C%20Size%3DRegular%2C%20State%3DOn.svg?alt=media&amp;token=d08029bc-cd20-4401-bc69-8ded58cdca38" alt="" data-size="line"> `Progress`
* Click the progress bar on the day you want to log an update
* Choose <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FdR0lJrFqzXRkwq77leCL%2FThumbs%20Up.svg?alt=media&amp;token=0b23234b-417e-4771-917f-6ea5a8299c64" alt="" data-size="line"> to mark it on track or improved, or <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FZpw6cJW8Cg2BiiaJP5Ua%2FStatus%20Buttons.svg?alt=media&amp;token=af2f2296-758f-428c-b53f-c71328d40ced" alt="" data-size="line"> to record a delay
* The progress bar will turn green or red based on the update type

See also: <a href="https://help.aphex.co/docs/planner/features/status.md" class="button secondary">Progress Updates</a>

## **Monitor Daily Task Progress**

***

See at a glance how many of your Tasks have been updated each day, with a live breakdown of what's on schedule, delayed or missing an update.

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2Fi0sKNLo5UJ5TVAFg7KMY%2FCompliance.png?alt=media&amp;token=e6c0a5a9-7898-4b04-9e0a-48c369228cc4" alt=""><figcaption></figcaption></figure>

* Click <kbd>View Options</kbd>
* Toggle <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FrvTcctNRDtoOHaw7U9zU%2FTheme%3DLight%2C%20Size%3DRegular%2C%20State%3DOn.svg?alt=media&amp;token=d08029bc-cd20-4401-bc69-8ded58cdca38" alt="" data-size="line"> Show Task Update Compliance
* Click <kbd>On Schedule</kbd>, <kbd>Delayed</kbd> or <kbd>Missing Update</kbd> to filter to just that day
* Optionally, click <kbd>Highlight Missing Updates</kbd> to show all missing updates of tasks today/past within the view
* Click <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FXgawm1OQ5MljhiqMGl55%2FButton.svg?alt=media&amp;token=f3c34361-1525-45ae-aff9-7d3947d84b89" alt="" data-size="line"> to dismiss

<details>

<summary>Task Update Compliance Logic &#x26; Rules</summary>

* Toggling on Task Update Compliance is per-user and won't affect anyone else's view
* Compliance counts update in real time
* Only Tasks visible in your current view and date range are counted
* If a Task is assigned to multiple people and appears in multiple Groups, it's only counted once

</details>

## Filtering the Board

***

Filters in Aphex let you show only what matters, whether that’s Tasks with certain properties, or ones that are missing something. Keep it simple or build something more detailed, it's up to you.

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FuNxWPKBfYRpo1oYLWm88%2FCX%20Everything%20File%20(6).png?alt=media&amp;token=f589d6ce-a2d1-496a-89d5-b0d088768803" alt=""><figcaption></figcaption></figure>

#### To filter a Board View:

* Click <kbd>Filters</kbd> at the top of the Board
* In the dropdown that appears select <kbd>Add Filters</kbd> and choose the property you'd like to filter by
* Change the logic from options like <kbd>Is</kbd> or <kbd>Contains</kbd> to <kbd>Is Not</kbd> or <kbd>Does Not Contain</kbd>  to hide or reveal the relevant Tasks
* Click to swap between <kbd>And</kbd>  and <kbd>Or</kbd>&#x20;

See also: creating & sharing <a href="https://help.aphex.co/docs/planner/features/view-controls.md" class="button secondary">Views</a>

<details>

<summary>Filter Logic &#x26; Rules</summary>

* All <a href="https://help.aphex.co/docs/account-and-task-properties/task-properties.md" class="button secondary">Task Properties</a> as well as <a href="https://help.aphex.co/docs/planner/features/readying-and-reviewing-plans.md#unresolved-issues" class="button secondary">Unresolved Issues</a> can be applied as a filter
* Archived values that are still in use will appear as filter options. Unused archived values will be hidden from the filter options
* Tasks that do not match the filter criteria will be hidden from the Board

</details>

## Customise Task Properties

***

Tailor your Board View to suit the way you plan & communicate. Adjust the layout, colour coding, visible days of the week and more.

<figure><img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FLGn3zUHgnkFqnMs6we21%2FCustomise%20Task%20Properties%20from%20Figma.png?alt=media&amp;token=06a42d7e-3ae0-4355-8222-ad012c2682a7" alt=""><figcaption></figcaption></figure>

#### To hide or reveal properties:

* Click <kbd>Layout & Properties</kbd> at the top left of the Board
* Toggle <img src="https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FrvTcctNRDtoOHaw7U9zU%2FTheme%3DLight%2C%20Size%3DRegular%2C%20State%3DOn.svg?alt=media&amp;token=d08029bc-cd20-4401-bc69-8ded58cdca38" alt="" data-size="line"> any property you'd like to display on the Task Cards
* Use the **`⋮⋮`** drag handles to reorder the properties on the Task Cards
* Optionally, click the `>` beside the property to open more options
* Use the ![](https://2273109354-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FLu0mYklsCTm7XQm3ZGqv%2Fuploads%2FtmKa0esyx9sHu9S2hGQX%2FVisibility.svg?alt=media\&token=3947542b-038d-492c-a254-3ea86e810728) to hide specific values within that property from view

## Customise the Board Layout

***

#### To change the visible days:

* Click <kbd>Layout & Properties</kbd>
* Select `Days`
* Pick from `5 Day`, `6 Day` or `7 Day`

#### To switch the Board Layout:

* Click <kbd>Layout & Properties</kbd>
* Select `Layout`
* Pick between `Waterfall` or `Masonry`

#### To colour code Task Cards on Board:

* Click <kbd>View Options</kbd>
* Select <kbd>Card Colour</kbd>
* Pick from <kbd>None</kbd>, <kbd>Owner</kbd>, <kbd>Subcontractor</kbd>, <kbd>Shift</kbd>, <kbd>Folder</kbd>, <kbd>Package</kbd>, <kbd>Location</kbd> or <kbd>Status</kbd>

<details>

<summary>Board View Options</summary>

| Colour        | Description                                                                                                    |
| ------------- | -------------------------------------------------------------------------------------------------------------- |
| None          | Plain Task Cards with no colour                                                                                |
| Owner         | The user colour of the Task Owner                                                                              |
| Subcontractor | The colour of the Task's Subcontractor on this Project                                                         |
| Shift         | The colour of the Task Shift                                                                                   |
| Folder        | The colour of the Folder the Task sits in directly. With Roll-up Folder on, the colour of the rolled-up Folder |
| Package       | The colour of the Task's Package                                                                               |
| Location      | The colour of the Task's Location                                                                              |
| Status        | Planned Tasks are orange, Promised Tasks are violet and Done Tasks are green                                   |

* Tasks with no value for the colour you pick (e.g. no Package) show as a plain card
* Your Card Colour is remembered for you and doesn't change the View for anyone else
* Relationship links can also be hidden or displayed by toggling the property on and off in the View Options menu.
  * Relationship links will be turned off when grouping by assignee.

</details>

See also: <a href="https://help.aphex.co/docs/planner/features/printing.md#print-board-view" class="button secondary">Print Board</a>


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://help.aphex.co/docs/planner/features/board.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.