Calendars
Who can use this feature?
Admin users can create, edit and archive the library of available Calendars.
Task Owners, Assignees and Admins can change the Calendar allocated to their Tasks.
Calendars define your project’s working and non-working days. Task durations are based only on the working days set in the assigned Calendar, so Tasks won’t be scheduled on non-working days.
Creating Calendars
Create a custom Calendar to set specific working and non-working days that match your project’s schedule.
To create a Calendar:
Click your Project Title in the top left, then select
Project AssetsSelect
Calendarsfrom the menuClick
Add a name and choose a colour to represent the Calendar
Pick your base Working Days
Click specific days on the Calendar to mark them as
WorkingorNon-WorkingexceptionsOptionally,
Click
Doneonce you're finished editingThe Calendar is added to the library of Calendars the team can assign to their Tasks
See also: Group Calendars
Aphex provided Calendars
Five Day
Monday, Tuesday, Wednesday, Thursday, Friday
Six Day
Monday, Tuesday, Wednesday, Thursday, Friday, Saturday
Seven Day
Monday, Tuesday, Wednesday, Thursday, Friday, Saturday, Sunday
Project Default Calendar
The default Calendar will be applied to all New Tasks created in the Project
If you change the default later, it won’t affect existing Tasks, they’ll stay on the calendar they were originally assigned
Non-Working Days
Adding non-working days to a Calendar will automatically prevent tasks from being scheduled on those days. You can create multiple calendars with different non-working patterns to suit your project.
Edit an existing Calendar
You can edit an existing Calendar to update working days, non-working days, change its name or colour.
To edit a Calendar:
Click your Project Title in the top left, then select
Project AssetsSelect
Calendarsfrom the menuHover over the existing Calendar
Click
then select
EditIf the Calendar is already in use, select whether to apply changes to existing Tasks or keep their current dates unchanged
Editing a Calendar in use
Making changes and saving a Calendar that is in use generates a prompt with the following options:
Save and hold dates on existing Tasks
The edited calendar will not be applied to any existing Tasks
Making any changes to the start date, end date or duration of a Task will apply the updated calendar to the Task
Save and force reschedule existing Tasks
The edited calendar will be applied to all future planned tasks and Tasks with days in progress
The edited calendar will not automatically be applied to any Tasks that have finished (no working days in progress or in the future)
Assigning Calendars to Tasks
Assigning a Calendar to a Task sets its working days and controls when it can start or finish.
To update the Calendar on a Task:
On the Gantt, navigate to the column picker
and toggle on
CalendarClick a cell in the column to add a Calendar to the Task from the dropdown
See the non-working days appear with reduced opacity on the Task Bar
See also: Bulk Edits
Calendar Property Rules
Each Task can have one Calendar assigned, you can’t add multiple calendars to a single Task
Archived Calendars will no longer appear as an available option to add to tasks, but will still exist on any tasks they were assigned to before they were archived
Filter by Calendar
Filter by Calendar to focus on Tasks working to a certain schedule.
To set a Calendar Filter:
Click
and
Select
Calendarin the first dropdownSelect from
IsorIs Notin the second dropdownSelect your desired Calendar in the third dropdown
See also: create & share Views
Last updated
Was this helpful?