Labour & Plant
Who can use this feature?
All project users can add Labour and Plant to their Tasks.
Project Admins can create new Labour and Plant resources.
Labour and Plant can be added to Tasks to track and forecast your daily resource demand.
Create Labour Resource
Creating Labour resource lets you build a reusable library of Labour to assign to Tasks.
To create Labour:
Click your Project Title in the top left, then select
Project AssetsSelect
Labourfrom the menuClick
Create your custom Labour resource by entering the
Name,Labour Typeand aColourThe Labour resource is added to the library of Labour the team can assign to their Tasks
Create Plant Resource
Creating Plant resource lets you build a reusable library of Plant to assign to Tasks.
To create Plant:
Click your Project Title in the top left, then select
Project AssetsSelect
Plantfrom the menuClick
Create your custom Plant resource by entering the
Name,Plant TypeandColourThe Plant resource is added to the library of Plant the team can assign to their Tasks
Plant Type
Access Equipment
Backhoe
Compacting Equipment
Concrete Placement
Concrete pumps
Cranes
Dozers
Dumper
Earthmoving Equipment
Excavators
Forklifts
Graders
Lifting Equipment
Marine Equipment
Other
Painting and Coating Equipment
Piling Equipment
Piling Rigs
Rollers
Small or Hand Tools
Tipper Lorrys (20 Tonne)
Trucks and Lorries
Wheeled Loaders
Assign Labour Resources to Tasks
You can assign as many Labour resources to each Task as you need. Once added to the task, they’re assumed to be needed for the entire working duration - keeping things simple and helping teams plan ahead.
To add Labour to a Task:
On the Gantt, navigate to the column picker
and toggle
LabourClick the Labour cell for your Task & select the relevant Labour option from the dropdown menu
Use the
+/-buttons to increase or decrease the Labour quantity needed for the duration of the Task
See also: Bulk Edits
Assign Plant Resources to Tasks
You can assign as many Plant resources to each Task as you need. Once added, they’re assumed to be needed for the entire working duration - keeping things simple and helping teams plan ahead.
To add Plant to a Task:
On the Gantt, navigate to the column picker
and toggle
PlantClick the Plant cell for your Task & select the relevant Plant option from the dropdown menu
Use the
+/-buttons to increase or decrease the Plant quantity needed for the duration of the Task
See also: Bulk Edits
Plant & Labour Property Rules
Labour & Plant are multi-select properties
You can assign multiple types of labour or plant to each Task
Each assigned item can have its own quantity
Quantities are applied per day
A quantity of 5 means 5 units are required for each day of the Task's duration
Quantities cannot vary across the days of a Task
Archived Labour & Plant resources will no longer be available to add to Tasks but will still exist on tasks it was assigned to before the resource was archived
View Forecasted Resources on the Gantt
Use the Resource Overlay in the Gantt to forecast Labour & Plant demand day by day. You'll see how much of each Labour or Plant is needed across the project, with a clear breakdown of which Tasks are driving that usage and who's using it.
To turn on the Labour Resource Overlay
Click
and select
ResourcesUse the icons on the left to view
LabourHover over the numbers to view your Total and Project Utilisation
Click
to filter to either
CreworIndividual ResourceClick the Resources Configuration icon
to switch between
Tasks in ViewandProject UtilisationHover over
to see the daily breakdown
To turn on the Plant Resource Overlay
Click
and select
ResourcesUse the icons on the left to view
PlantHover over the numbers to view your Total and Project Utilisation
Click
to filter to a specific Plant Type
Click the Resources Configuration icon
to switch between
Tasks in ViewandProject UtilisationHover over
to see the daily breakdown
See also: Export Resource Demand
What's Shown on Hover
On hover, the daily breakdown includes:
Utilisation
Quantity of Material used by Tasks in your current View (respects filters)
# no of Tasks
Number of Tasks in your current View using that Material on the selected day (respects filters)
Project Utilisation
Total quantity used across the entire project (ignores filters)
# no of Project Tasks
Number of Project-wide Tasks using that material on the selected day (ignores filters)
Task Owner Breakdown
Lists each Task Owner contributing to Project usage
Includes Task Count and percentage of total utilisation for that day and Material
Cell shading
Darker = higher quantity
Lighter - lower quantity
Scale is relative to the values shown in the current overlay
Quantity values are only shown in Day View
In Week, Month or Year mode, cell shading remains but numeric values are hidden
Resource Overlay Configuration Options
Total
The demand for tasks in your current view
Project Utilisation
The demand for your entire project
Hide Un-utilised resources
Removes resources that aren’t assigned to any Tasks from the resource list
Filter by Labour
Filter by Labour to quickly review and manage work related to a particular Labour item across your plan.
Filter by Labour:
Click
and
Select
Labourin the first dropdownSelect from
Is,Is Not,Is Empty,Is Not Emptyin the second dropdownSelect your desired Labour item in the third dropdown
Filter by Plant
Filter by Plant to quickly review and manage work related to a particular Plant item across your plan.
To filter by Plant:
Click
and
Select
Plantin the first dropdownSelect from
Is,Is Not,Is Empty,Is Not Emptyin the second dropdownSelect your desired Plant item in the third dropdown
See also: create & share Views
Filter Breakdown
Labour
Is Is Not Is Empty Is Not Empty
Multi-Select
Plant
Is Is Not Is Empty Is Not Empty
Multi-Select
Report on Labour and Plant Demand
Power BI
Connect your Project as a datasource for Power BI to report on Labour & Plant Demand.
Aphex Insight
Utilise Aphex Insight to track Labour & Plant Resource Demand. See trends and drill down into specific Tasks to identify where each Labour and Plant Resource is allocated.
See also: Connect to Power BI
Last updated
Was this helpful?