Gantt Views can be grouped by different properties within your plan to organise your Tasks in different ways.
To change how the Gantt is Grouped:
Click the menu in the top left of the Gantt
Select a Primary Grouping. Pick from Folder, Owner, Package, Shift or Location
Optionally, select a Sub-Grouping to apply another level of structure beneath the Primary Group
When Hide Empty Primary Groups is , only Groups that contain visible Tasks will show on the Gantt. Any Groups without Tasks in your current View will be hidden.
Click the menu in the top left of the Gantt
Select either Collapse All or Expand All
Gantt Views are very flexible and allow you to visualise any set of Tasks over time.
To change the visible Date Range on the Gantt:
Click at the top of the Gantt
Yours might also look similar to or
Choose your preferred mode from the selector:
Filters in Aphex let you show only what matters, whether that’s Tasks with certain properties, or ones that are missing something. Keep it simple or build something more detailed, it's up to you.
To filter the Tasks you see in a Gantt View:
Click at the top of the Gantt
In the dropdown that appears select and choose the property you'd like to filter by
Change the logic from options like or to or to hide or reveal the relevant Tasks
Click to swap between and
Using Filter Groups:
Groups are helpful when combining logic and logic in your filter
Click to create an additional filter group
See also: creating & sharing
If your Gantt looks empty, it's usually because settings like Filters, your Date Range, or the Hide Empty Groups toggle are hiding your tasks or groups. Aphex provides clear messages and icons to help you adjust your view.
Empty Gantt Message:
When no tasks or groups are visible, a message will appear in the Gantt:
Looks like your Gantt is empty Try adjusting or to reveal activities and groups
To reveal your tasks, simply click the highlighted or in the message to open the relevant panel and adjust your view settings.
Hidden Groups Notification:
When the Hide Empty Groups toggle is active, a notification appears at the top of the Gantt if any groups (Folder, Location, Owner, Package, Shift or Subcontractor) are hidden as a result:
[X] Hidden [Group Type] Adjust your and configuration to reveal hidden groups
To reveal hidden groups:
Click the highlighted or in the message to open the relevant panel and adjust your view settings.
Open [View Settings Icon] and set the Hide Empty Groups toggle to [Toggle Off Icon].
Hidden Items in Folders:
Look for the next to a Folder Row. This icon indicates the folder contains subfolders, but they are hidden by your current Filters, Date Range, or Hide Empty Toggle.
To temporarily reveal the hidden folers:
Click the next to the folder name. This displays the contents without changing your overall Gantt view.
Tasks on the Gantt will always be sorted by Start Date - the earlier a Task starts, the higher it will appear within it's grouping.
Aphex will hold the position of your Tasks while you make edits, and then when you're ready to re-apply the Sort Order, click in the bottom left corner.
Refreshing your Aphex window will also trigger the sort order to be re-applied to your Gantt View.
You can view your projects on a range of time scales, from a single day to a full year:
Head to the bottom-right corner of your Gantt
Use the menu to switch between Day, Week, Month, or Year
The Gantt will instantly update to show your plan on the scale you’ve selected
Overlays let you layer in things like baselines, critical path visibility, or daily resource demand. This means you can add extra context to your Gantt without changing up or leaving your View.
Click at the top of the Gantt
Select from Resource, Baseline, Critical Path
To compare the Live Plan to a previous week, select Baseline
See also: and
When viewing your Gantt, Aphex automatically calculates a Start Date, End Date, and Duration for Folders, Packages, and Parent Tasks. These adjust based on what’s visible in your View and which working calendar you chose to apply.
Click
Select Group Duration Calendar
Choose one out of: Project Default, 5 Day Week, 7 Day Week
Open the Column Picker and toggle Duration or Start / End
These values change dynamically with Filters or Date Range updates
Filtered values are marked with a icon so you know they’ve been adjusted
See also:
Turn on any Task Property as a spreadsheet-style column, then click into cells to edit, bulk-fill, or paste across Tasks.
To hide and show Gantt Columns:
Click the button at the top of the Gantt
Set the toggles to or to hide or reveal any combination of columns
Once a column is enabled, select any cell to change the value
Every colour and icon on the Gantt tells you something. Whether it’s a Milestone, a delay, or who is responsible for the work - you can choose what shows and how it looks.
Click in the top right of the Gantt
Select Bar Colour
Choose how you’d like to colour the Gantt; by Subcontractor, Shift, or Owner
Milestones will appear as and any associated Target Dates will be if slipped and if on track
Overdue Blockers will be represented with next to the end of the Task
Delays are shown as a on the Task Bar, displaying the total amount of days the Task has been delayed by
Click and toggle
See also:
Use the Gantt search to quickly find Tasks. As you type, matching Tasks are highlighted and jumped into view automatically.
To Search for Tasks:
Click into the Search Bar in the top left of the Gantt
Type in your search term
Press Enter on your keyboard or click the < and > icons to cycle through all matching Tasks
- Enter the number of days before and/or after today to create a moving window.
- Pick specific start and end dates using the date pickers.
Optional: Toggle "Show Surrounding Weeks" to add an extra week of visibility on either side of your selection
This will show a list of all Published Versions, and all Master Schedule Imports
Select any option to see how how your current plan compares to your baseline
Hover over the icon to see:
The Filtered value
The Total value
Your Gantt will update instantly to reflect the new colour scheme
Show Progress and Show Overdue Blockers to hide these Icons from the Gantt


X Week Lookahead
Today + (Project Lookahead Period)
Next 30 Days
Today + Next 30 Days
Next 3 Months
Today + Next 12 Weeks
Next 6 Months
Today + Next 25 Weeks
Next 12 Months
Today + Next 52 Weeks
All Future Tasks
From Today to Last Task
Project to Date
From First Task to Today
All Tasks
From First Task to Last Task
Forwards
Today + specified days into future
Backwards
Today - specified days into past
Combined
Start Date
Selected start date
End Date
Selected end date
Combined
Off (default)
Displays exactly the calculated range, no additions
On
Adds 1 week before start date + 1 week after end date to visible area
5 Day Week
(Mon–Fri) Static calendar
7 Day Week
(Mon–Sun) Static calendar
Ctrl + 1
All required columns
Ctrl + 2
Time columns
Ctrl + 3
User columns
Ctrl + 4
Resource columns
Ctrl + 5
Map columns
Ctrl + 6
Structure columns
Ctrl + 7
Other columns
Ctrl + 8
Copy
Ctrl + C
Paste
Ctrl + V
Select multiple cells
Shift + Click (cell)
Select multiple tasks
Shift + Click (checkbox)
Undo
Ctrl + Z
Redo
Shift + Ctrl + Z
New line
Shift + Enter
Move task and break links
Shift + Click + Drag (task)
Duplicate Task
Ctrl + D
Full rolling window centred on today
Fixed range from start to end date