Aphex Help
Go to Aphex
  • Welcome
  • Getting Started
    • Joining your Team
      • Getting Around
      • Adding Tasks
      • Linking Tasks
      • Resources
      • Map & Location
      • Readying & Publishing Plans
    • Project Set Up
      • Importing
      • Folders & Structure
      • Users
      • Views
      • Resources & Assets
      • Map
      • Publishing & Routine
  • Guides
    • Imports
      • Importing your Master Schedule (XML)
      • Migrate existing plans to Aphex (CSV)
      • Importing Folders (CSV)
    • Feature Walkthroughs
      • Creating & Sharing Published Versions
      • Understanding Resources in the Plan
      • Exporting Data to a CSV
      • Copying tasks between Projects
      • Blockers
    • Integrations
      • ArcGIS Set Up Guide
      • Getting Started with Power BI Reporting
    • Reporting
      • Power BI Templates
  • Reference Docs
    • Fundamentals
      • Organisations
      • Projects
      • Tasks
      • Task Panel
      • User Preferences and Notifications
    • Scheduling
      • Views
      • Gantt
      • Board
      • List
      • Map and Clashes
      • Status and Progress Updates
    • Project Assets
      • Project Users and Teams
      • Resources and Assets
      • Structure
    • Publish, Print & Share
      • Printing
      • Published Versions and Shared Plans
      • Readying and Reviewing Plans
    • Data
      • Imports and Exports
      • Transferring
  • Frequently Asked
    • FAQs
      • How do I Add & Remove Filters?
      • How do I create & track Milestones?
      • How do I Move Folders?
      • How to login with SSO
      • Where have my Tasks gone?
      • How do I print my Plan?
      • Can I change the sort order of Tasks and Packages?
      • How is PPC calculated in the Power BI dashboard?
      • Why can't I delete a Task?
      • Why are the successors not scheduling?
      • How do I promise Tasks?
      • How do I delete multiple Tasks?
      • Why were some Tasks skipped from updating?
      • Why can't I upload an image for my Location?
      • How do I change the non-working days of a Task?
      • How do I make changes in bulk?
      • How do I transfer my work to another User?
      • How do I add new Users to the Project?
      • What can Lite users do?
      • How do I set a Reviewer?
      • How do I reset my Password?
      • How do I set up MFA?
      • Setting up SAML SSO
      • How can I use Aphex to update P6?
    • Troubleshooting
      • Troubleshooting Aphex
      • Troubleshooting your ArcGIS integrations
    • Coming Soon
      • 2025 Pricing Update
      • Changes to View Controls & Filters
      • Changes to the WBS
      • Changes with Status
  • Policies
    • Terms & Policies
      • Compliance and Certification
      • Terms & Agreements
        • Terms of Service Overview
        • Terms of Service
        • Subprocessors List
        • Service Level Agreement
      • Policies
        • Acceptable Use Policy
        • Privacy Policy
        • Cookie Policy
        • Fair Billing Policy
        • Support Policy
  • DEVELOPER
    • API & Integration
      • Plan APIs
        • Authentication
        • Project Assets
        • Tasks
      • Published Plans (Power BI) API
      • Work Area API
Powered by GitBook
On this page

Was this helpful?

  1. Frequently Asked
  2. FAQs

How is PPC calculated in the Power BI dashboard?

Last updated 10 months ago

Was this helpful?

If you've downloaded one of our , then you may have questions about how the PPC (percent plan complete) is being calculated.

Here's a quick summary:

The PPC of a task is the percentage of the days of planned work that happened between last week and now (or any two publication dates).

Example:

If you had three tasks;

  • Task A - 3-day tasks all planned to occur in the reference week

  • Task B - 2-day task all planned to occur in the reference week

  • Task C - 4-day task with two days planned in the reference week and two days the following week

With these outcomes;

  • Task A - all three days occurred during the reference week

  • Task B - slipped, and one of the days occurred in the reference week

  • Task C - slipped, and one of the days occurred in the reference week

  • Task A - 3 / 3 days = 100% PPC

  • Task B - 1 / 2 days = 50% PPC

  • Task C - 1 / 2 days = 50% PPC

So your total PPC would be AVERAGE(A, B and C) = 66%