How is PPC calculated in the Power BI dashboard?
Last updated
Was this helpful?
Last updated
Was this helpful?
If you've downloaded one of our , then you may have questions about how the PPC (percent plan complete) is being calculated.
The PPC of a task is the percentage of the days of planned work that happened between last week and now (or any two publication dates).
Example:
If you had three tasks;
Task A - 3-day tasks all planned to occur in the reference week
Task B - 2-day task all planned to occur in the reference week
Task C - 4-day task with two days planned in the reference week and two days the following week
With these outcomes;
Task A - all three days occurred during the reference week
Task B - slipped, and one of the days occurred in the reference week
Task C - slipped, and one of the days occurred in the reference week
Task A - 3 / 3 days = 100% PPC
Task B - 1 / 2 days = 50% PPC
Task C - 1 / 2 days = 50% PPC
So your total PPC would be AVERAGE(A, B and C) = 66%