Aphex Help
Go to Aphex
  • Welcome
  • Getting Started
    • Joining your Team
      • Getting Around
      • Adding Tasks
      • Linking Tasks
      • Resources
      • Map & Location
      • Readying & Publishing Plans
    • Project Set Up
      • Importing
      • Folders & Structure
      • Users
      • Views
      • Resources & Assets
      • Map
      • Publishing & Routine
  • Guides
    • Imports
      • Importing your Master Schedule (XML)
      • Migrate existing plans to Aphex (CSV)
      • Importing Folders (CSV)
    • Feature Walkthroughs
      • Creating & Sharing Published Versions
      • Understanding Resources in the Plan
      • Exporting Data to a CSV
      • Copying tasks between Projects
      • Blockers
    • Integrations
      • ArcGIS Set Up Guide
      • Getting Started with Power BI Reporting
    • Reporting
      • Power BI Templates
  • Reference Docs
    • Fundamentals
      • Organisations
      • Projects
      • Tasks
      • Task Panel
      • User Preferences and Notifications
    • Scheduling
      • Views
      • Gantt
      • Board
      • List
      • Map and Clashes
      • Status and Progress Updates
    • Project Assets
      • Project Users and Teams
      • Resources and Assets
      • Structure
    • Publish, Print & Share
      • Printing
      • Published Versions and Shared Plans
      • Readying and Reviewing Plans
    • Data
      • Imports and Exports
      • Transferring
  • Frequently Asked
    • FAQs
      • How do I Add & Remove Filters?
      • How do I create & track Milestones?
      • How do I Move Folders?
      • How to login with SSO
      • Where have my Tasks gone?
      • How do I print my Plan?
      • Can I change the sort order of Tasks and Packages?
      • How is PPC calculated in the Power BI dashboard?
      • Why can't I delete a Task?
      • Why are the successors not scheduling?
      • How do I promise Tasks?
      • How do I delete multiple Tasks?
      • Why were some Tasks skipped from updating?
      • Why can't I upload an image for my Location?
      • How do I change the non-working days of a Task?
      • How do I make changes in bulk?
      • How do I transfer my work to another User?
      • How do I add new Users to the Project?
      • What can Lite users do?
      • How do I set a Reviewer?
      • How do I reset my Password?
      • How do I set up MFA?
      • Setting up SAML SSO
      • How can I use Aphex to update P6?
    • Troubleshooting
      • Troubleshooting Aphex
      • Troubleshooting your ArcGIS integrations
    • Coming Soon
      • 2025 Pricing Update
      • Changes to View Controls & Filters
      • Changes to the WBS
      • Changes with Status
  • Policies
    • Terms & Policies
      • Compliance and Certification
      • Terms & Agreements
        • Terms of Service Overview
        • Terms of Service
        • Subprocessors List
        • Service Level Agreement
      • Policies
        • Acceptable Use Policy
        • Privacy Policy
        • Cookie Policy
        • Fair Billing Policy
        • Support Policy
  • DEVELOPER
    • API & Integration
      • Plan APIs
        • Authentication
        • Project Assets
        • Tasks
      • Published Plans (Power BI) API
      • Work Area API
Powered by GitBook
On this page
  • Group By
  • Task Properties
  • Progress Updates

Was this helpful?

  1. Reference Docs
  2. Scheduling

List

List is a quick and simple way to see tasks within your project in a list. These are shown in daily increments, making it easy to see what's going on in the project for that day.

Group By

You can choose how tasks are organised in List view by setting the Grouping.

The Primary and Sub-Groups you can pick from are:

  • None

  • Schedule

  • Owner

  • Assignee

  • Subcontractor

  • Location

  • Shift

Task Properties

You can choose which Task properties are visible on the task card.

The Task properties you can pick from are:

  • Assignees

  • Calendar

  • Dates

  • Labour

  • Location

  • Materials

  • Notes

  • Owner

  • Package

  • Plant

  • Progress

  • Shift

  • Status

  • Subcontractor

  • Folder

  • Tags

  • Blockers

Progress Updates

For each working day of a Task, Progress Updates can be recorded to indicate performance. Each Progress Update includes the following data:

Progress Update Property
Description

Date

Selected working day to record the event against

Type

Delayed

On Schedule

Task is on Schedule for that day

Improved

Task has been Shortened or Moved to an earlier date

Reason

Reason for the change. This can be configured by each project individually and typically contains reasons such as "Awaiting Access".

Amount

Impact of the update is recorded in a Value that represents a duration in working days (+ or -)

Added By

User who recorded the update

Created At

Timestamp of when the update was recorded

Progress Updates: Type

There are different types of Progress Updates:

Name
Description

Delayed

A task’s end date has been delayed from the prior plan or commitment

On Schedule

A task’s end date is confirmed as achievable.

Improved

A task’s end date has been improved (brought earlier).

Task Status Change

A task’s meta status has changed aka Promised, Planned, Done

Ripple Status

If a Promised task is delayed, the same delay (amount & reason) can be applied to all following Promised tasks, given the User has the correct permissions over the predecessor Tasks.