Aphex Help
Go to Aphex
  • Welcome
  • Getting Started
    • Joining your Team
      • Getting Around
      • Adding Tasks
      • Linking Tasks
      • Resources
      • Map & Location
      • Readying & Publishing Plans
    • Project Set Up
      • Importing
      • Folders & Structure
      • Users
      • Views
      • Resources & Assets
      • Map
      • Publishing & Routine
  • Guides
    • Imports
      • Importing your Master Schedule (XML)
      • Migrate existing plans to Aphex (CSV)
      • Importing Folders (CSV)
    • Feature Walkthroughs
      • Creating & Sharing Published Versions
      • Understanding Resources in the Plan
      • Exporting Data to a CSV
      • Copying tasks between Projects
      • Blockers
    • Integrations
      • ArcGIS Set Up Guide
      • Getting Started with Power BI Reporting
    • Reporting
      • Power BI Templates
  • Reference Docs
    • Fundamentals
      • Organisations
      • Projects
      • Tasks
      • Task Panel
      • User Preferences and Notifications
    • Scheduling
      • Views
      • Gantt
      • Board
      • List
      • Map and Clashes
      • Status and Progress Updates
    • Project Assets
      • Project Users and Teams
      • Resources and Assets
      • Structure
    • Publish, Print & Share
      • Printing
      • Published Versions and Shared Plans
      • Readying and Reviewing Plans
    • Data
      • Imports and Exports
      • Transferring
  • Frequently Asked
    • FAQs
      • How do I Add & Remove Filters?
      • How do I create & track Milestones?
      • How do I Move Folders?
      • How to login with SSO
      • Where have my Tasks gone?
      • How do I print my Plan?
      • Can I change the sort order of Tasks and Packages?
      • How is PPC calculated in the Power BI dashboard?
      • Why can't I delete a Task?
      • Why are the successors not scheduling?
      • How do I promise Tasks?
      • How do I delete multiple Tasks?
      • Why were some Tasks skipped from updating?
      • Why can't I upload an image for my Location?
      • How do I change the non-working days of a Task?
      • How do I make changes in bulk?
      • How do I transfer my work to another User?
      • How do I add new Users to the Project?
      • What can Lite users do?
      • How do I set a Reviewer?
      • How do I reset my Password?
      • How do I set up MFA?
      • Setting up SAML SSO
      • How can I use Aphex to update P6?
    • Troubleshooting
      • Troubleshooting Aphex
      • Troubleshooting your ArcGIS integrations
    • Coming Soon
      • 2025 Pricing Update
      • Changes to View Controls & Filters
      • Changes to the WBS
      • Changes with Status
  • Policies
    • Terms & Policies
      • Compliance and Certification
      • Terms & Agreements
        • Terms of Service Overview
        • Terms of Service
        • Subprocessors List
        • Service Level Agreement
      • Policies
        • Acceptable Use Policy
        • Privacy Policy
        • Cookie Policy
        • Fair Billing Policy
        • Support Policy
  • DEVELOPER
    • API & Integration
      • Plan APIs
        • Authentication
        • Project Assets
        • Tasks
      • Published Plans (Power BI) API
      • Work Area API
Powered by GitBook
On this page
  • Supported Master Schedules
  • Bringing in your Project Assets (Optional)
  • Importing Milestones
  • Create your Import File
  • Importing your Master Schedule
  • Distributing Work

Was this helpful?

  1. Getting Started
  2. Project Set Up

Importing

Last updated 4 months ago

Was this helpful?

Things to know before you start:

  • You must export your Master Schedule to .XML format

  • You must be a Project Admin to run an import

  • Your Organisation must be on the Pro, Pro+ or Enterprise Plan

  • If you are looking for a more in depth guide on setting up your XML, please head to

Supported Master Schedules

Aphex currently supports .XML imports from:

  • Primavera P6

  • Microsoft Project

  • Asta Powerproject

Bringing in your Project Assets (Optional)

You can bring Project Assets into Aphex to save time. These can be pre-assigned to your tasks on your Master Schedule. These Project Assets include:

  • Create a User Defined Field (UDF) for each asset you wish to import.

  • Name each UDF something recognisable, like “Aphex Subcontractor”.

  • In each UDF (eg. Subcontractor or Location), insert the field (Subcontractor, location etc.) for each activity. This should be consistent with the name in your Aphex project (if not, Aphex will create a new one)

  • In the Owner UDF, insert the email address of the activity’s owner. Check that this matches the email address the team member uses for Aphex. If not, the address entered will receive an invite to join the project.

Importing Milestones

Milestones can be imported into Aphex in bulk from your Master Schedule. These will be automatically imported with your regular tasks & do not need to be mapped.

Follow these steps to create Milestones in your respective program:

  • Add a new Activity (or select one that you have already made)

  • Go to the Details window

  • Select the General Tab & head to the Activity Type dropdown

  • Change the 'Task Dependant' to either 'Start Milestone' or 'Finish Milestone'

  • Create a Task

  • Enter 0 into the duration column & hit Enter

  • This will create a Milestone

  • Aphex Milestones have a duration of at least 1 day. If your imported Milestone is 0 days, this will be updated to 1 day duration in Aphex

  • Aphex does not differentiate Start Milestones & Finish Milestones, so these will just be imported as 'Milestones'

  • A Target Date can be set in Aphex to track the progress of your Milestones

Create your Import File

Your .xml file will need to be formatted correctly to be imported into Aphex. Our supported tools each have guides on how to do this if you get stuck:

Importing your Master Schedule

Upload

  • Click the Aphex Icon in the top left, above the Gantt

  • Click Master Schedule Imports

  • From the Master Schedule Imports page, click Import and select the .XML file you'd like to upload

Filter [Optional]

If you created a UDF filter in your master schedule, select the UDF and value from the two drop-down lists.

Timeframe

Select the timeframe of data that you’d like to import. You can see the number of tasks each timeframe will import from your .XML file.

Check Unsupported Task Types

If your Import file contains WBS Summaries or Level of Effort (LoE) Tasks, you can choose how to handle these tasks.

For WBS Summaries, you can choose to:

  • Ignore them from the import so they will be excluded.

  • Import as Tasks. If imported, WBS summaries will convert to Task Dependant types.

For Level of Effort (LoE) Tasks you can select from:

  • Ignore all LoE tasks and these will not be imported (this is the recommended option)

  • Import LoE tasks as task dependant types without links

  • Import LoE tasks as task dependant types with links - Selecting this option may cause variance in your import

Check Driving Predecessors

There may be some Tasks that are being driven by Tasks outside of your import dates. This can sometimes result in variance. The decisions for this step include:

For Driving Predecessor Tasks, you can choose to:

  • Add missing Tasks to the import scope (this is the recommended option)

  • Remove non-driving Links between selected Tasks.

  • Do nothing

For Driving Predecessors Level of Effort Tasks you can select from:

  • Remove non-driving Links between selected Tasks (this is the recommended option)

  • Add missing Tasks to the import scope

  • Do nothing

Handle Actual Dates

Aphex uses Task Status to define a Task state & scheduling behaviour. Decide how you would like to handle tasks with Actual Dates.

For Actual Starts, you can choose to:

  • Import without Predecessor Links (this is the recommended option)

  • Import with Predecessor Links

For Actual Finishes you can select from:

  • Set Task Status to Done (this is the recommended option)

  • Do nothing

Set Target Dates from Milestones

Choose whether to set Target Dates when importing Milestones in Aphex. Options include:

  • Set Milestone Target Date from the imported Dates

  • Do nothing

Target Dates will be automatically set as the date of the Milestone when it is imported. This can be changed once the Milestone has been imported.

Map Task Properties [Optional]

  • To import your current WBS into your Project's Folder tree, select the WBS option from the Folder Code drop-down list.

  • If you've chosen to pre-assign project assets, you’ll need to select the correct field on each drop-down list so that Aphex can correctly map your UDFs to your imported activities.

Review and Import

The final import page summarises the data you will be importing, including the number of tasks, Folder codes, Owner, Subcontractors, Locations, Notes and Calendars.

This will also be where you can see if there were any Tasks or Properties that were skipped.

Once you’re happy with your options, click Finish Import to import your Master Schedule.

Distributing Work

Your imported Tasks will be imported into Project Data. The next steps will be to assign the tasks to their Owners & then move them from the Backlog onto the Gantt.

  • Click the Aphex icon in the top left, above the Gantt

  • Click Master Schedule Imports, then navigate to the Project Data page using the side-menu

  • Open the Unassigned tab

  • Select an owner for each task with the drop-down menu

  • Click Move Tasks to Backlog

  • Select the Backlog tab

  • To select all of the Tasks in the Backlog, click the checkbox at the top of the table

  • Click the Move Tasks to Gantt button to move the Tasks onto the Gantt

Importing your Master Schedule
Primavera P6
Microsoft Project
Asta Powerproject